47PC0223F0023
TO PROVIDE CONSTRUCTION SERVICES FOR THE HANLEY 13 FLOOR ATF PROJECT IN THE AMOUNT OF $1,603,831.24.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | General Services Administration |
| Office | PBS R2 REPAIR AND ALTERATIONS BRANCH |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Z2AA — REPAIR OR ALTERATION OF OFFICE BUILDINGS |
| Parent award / vehicle | 47PC0220D0003 |
| Set-aside | SMALL BUSINESS SET ASIDE - TOTAL |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $1.8M |
| Current contract value | $1.8M |
| Potential contract value / ceiling | $1.8M |
| Start date | Feb 23, 2023 |
| Current end date | Oct 30, 2025 |
| Potential end date | Dec 30, 2025 |
| Latest award activity | Oct 17, 2025 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 6 of 6 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Oct 17, 2025 | PS0013 | $75.1K | TO INCORPORATE CLIN 0011 FOR ELECTRICAL CHANGES FOR THE ATF SYRACUSE-HANLEY CONSOLIDATION- CONSTRUCTION PROJECT LOCATED IN THE JAMES M. HANLEY FEDERAL BUILDING IN SYRACUSE, NY. TO EXTEND THE COMPLETION DATE TO 10/30/25 AND ULTIMATE DATE TO 12/30/25. |
| Aug 29, 2025 | PS0012 | $-102.9K | THIS MOD IS TO INCORPORATE THE SOW DATED 1/29/25. THIS DECREASES THE AWARD TOTAL FROM $1,785,163.66 TO $1,682,269.99, EXTENDS THE POP COMPLETION DATE FROM 6/13/25 TO 9/30/25 AND EXTENDS THE ESTIMATED ULTIMATE COMPLETION DATE FROM 8/13/25 TO 11/30/25 |
| May 14, 2025 | PA0011 | $0 | THE MODIFICATION IS TO UPDATE THE FUNDING FIXED ASSET RNY12915NY0281ZZ INFORMATION FROM CIPIMP TO IMPROVMNT IN THE ACCOUNTING LINES OF THIS AWARD. THIS IS AN ADMINISTRATIVE CHANGE TO THE ACCOUNTING ONLY, ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME |
| Apr 10, 2025 | PS0010 | $0 | THIS TIME EXTENSION MOD FOR THE ATF SYRACUSE-HANLEY CONSOLIDATION PROJECT- CONSTRUCTION PROJECT IS TO EXTEND THE PERIOD OF PERFORMANCE COMPLETION DATE FROM 1/03/25 TO 6/13/25 AND EXTENDS THE ESTIMATED ULTIMATE COMPLETION DATE FROM 3/03/25 TO 8/13/25 |
| Mar 28, 2025 | PA0009 | $0 | THIS ADMINISTRATIVE MODIFICATION FOR THE ATF SYRACUSE-HANLEY CONSOLIDATION PROJECT- CONSTRUCTION CONTRACT IS TO TRANSFER ALL CONTRACTING OFFICERS REPRESENTATIVE'S (COR) RESPONSIBILITIES FROM KAREN SHONBORN TO ANDREW WOODRING |
| Nov 25, 2024 | PS0008 | $5.8K | THIS MOD IS TO INCORPORATE THE ATTACHED SOW DATED JULY 30TH, 2024 AND ALSO EXTENDS THE PERIOD OF PERFORMANCE COMPLETION DATE FROM 11/01/24 TO 1/03/25 FOR THE ATF HANLEY-CONSTRUCTION PROJECT AT JAMES HANLEY FOB, SYRACUSE, NY. |
Research next steps
- Verify whether remaining options may extend performance beyond the current end date.
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.