47PC0223F0033
CONSTRUCTION MANAGEMENT SERVICES FOR THE CHILDCARE BALLISTIC RESISTANT AND SECURITY IMPROVEMENTS PROJECT AT THE JACOB JAVITS FOB IN NY.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | General Services Administration |
| Office | PBS R2 REPAIR AND ALTERATIONS BRANCH |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | R499 — Other Professional Services |
| Parent award / vehicle | 47PD0319A0010 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $174.9K |
| Current contract value | $174.9K |
| Potential contract value / ceiling | $174.9K |
| Start date | Mar 21, 2023 |
| Current end date | Mar 29, 2026 |
| Potential end date | Mar 29, 2026 |
| Latest award activity | Mar 16, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 8 of 8 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Mar 16, 2026 | PS0011 | $0 | UPDATE THE CONTRACT END DATE FROM 3/8/2026 TO 3/29/2026 AT NO ADDITIONAL COST. THIS UPDATE IS TO ALIGN WITH THE ACTUAL START DATE OF THE 30 DAYS CLOSEOUT PHASE PER THE SUBSTANTIAL COMPLETION DATE OF 2/27/2026. |
| Mar 12, 2026 | PA0010 | $0 | ADMINISTRATIVE MODIFICATION TO UPDATE OF THE FUNDING FIXED ASSET INFORMATION IN THE ACCOUNTING STRINGS. |
| Feb 11, 2026 | PS0009 | $4.5K | THREE WEEKS EXTENSION OF CM SERVICES DUE TO GC CONTRACTOR DELAYS. |
| Dec 15, 2025 | PS0008 | $1.4K | SIX WEEKS EXTENSION CMA SERVICES IN SUPPORT OF EXTENDED CONSTRUCTION PHASE. |
| Oct 31, 2025 | PS0007 | $9.7K | EXTENSION OF 28 CALENDAR DAYS TO CM SUPPORT SERVICES DURING GC EXTENDED CONSTRUCTION PHASE. |
| Jul 28, 2025 | PS0006 | $2.6K | EXTENSION OF CM SERVICES (4 MONTHS) IN SUPPORT OF THE EXTENDED CONSTRUCTION PHASE. |
| Apr 25, 2025 | PS0005 | $13.3K | EXTENSION OF CM SERVICES FOR AN ADDITIONAL (12) TWELVE WEEKS IN SUPPORT OF THE EXTENDED CONSTRUCTION PHASE DUE TO DELAYS CAUSED BY MANUFACTURING ISSUES UNDER THE GC CONTRACT. |
| Jan 10, 2025 | PS0004 | $20.4K | 12 WEEKS EXTENSION OF CM SERVICES IN SUPPORT OF THE EXTENDED CONSTRUCTION PHASE UNDER THE GC CONTRACT FOR THE CHILDCARE BALLISTIC RESISTANT AND SECURITY IMPROVEMENTS PROJECT AT THE JACOB JAVITS FOB, NEW YORK. |