Federal contract award
47PC0225F0011
THE AWARD FOR THE KEATING HARDENING PHASE II- DESIGN PROJECT LOCATED IN ROCHESTER, NY FOR THE TOTAL OF $166,178.95 IS FOR THE WORK DESCRIBED IN THE SOW DATED 11/21/24. THE PERIOD OF PERFORMANCE COMPLETION DATE IS 7/30/25.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | General Services Administration |
| Office | PBS R2 REPAIR AND ALTERATIONS BRANCH |
| NAICS | 541310 — Architectural Services |
| PSC | C1AA — ARCHITECT AND ENGINEERING- CONSTRUCTION: OFFICE BUILDINGS |
| Parent award / vehicle | 47PC0321D0004 |
| Set-aside | SMALL BUSINESS SET ASIDE - TOTAL |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $166.2K |
| Current contract value | $166.2K |
| Potential contract value / ceiling | $166.2K |
| Start date | Feb 28, 2025 |
| Current end date | Aug 22, 2026 |
| Potential end date | Oct 22, 2026 |
| Latest award activity | May 13, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 5 of 5 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 13, 2026 | PS0004 | $0 | THIS MOD IS FOR A NO-COST TIME EXTENSION FOR THE KEATING HARDENING PHASE II- DESIGN PROJECT THAT EXTENDS THE CONTRACT COMPLETION DATE FROM 5/24/26 TO 8/22/26 AND THE ULTIMATE COMPLETION DATE (CLOSEOUT) FROM 7/24/26 TO 10/22/26 |
| Jan 28, 2026 | PS0003 | $0 | THIS NO COST TIME EXTENSION MOD FOR THE KEATING HARDENING PHASE II- DESIGN PROJECT IS TO EXTEND THE PERIOD OF PERFORMANCE COMPLETION DATE FROM 1/24/26 TO 5/24/26, AND EXTENDS THE ULTIMATE ESTIMATED COMPLETION DATE (CLOSEOUT) FROM 3/24/26 TO 7/24/26 |
| Oct 10, 2025 | PS0002 | $0 | THIS NO COST TIME EXTENSION MOD FOR THE KEATING HARDENING PHASE II- DESIGN PROJECT IS TO EXTEND THE PERIOD OF PERFORMANCE COMPLETION DATE FROM 9/26/25 TO 1/24/26, AND EXTENDS THE ULTIMATE ESTIMATED COMPLETION DATE (CLOSEOUT) FROM 11/26/25 TO 3/24/26 |
| Jul 24, 2025 | PS0001 | $0 | KENNETH B. KEATING FEDERAL BUILDING, ROCHESTER NY IS TO EXTEND THE PERIOD OF PERFORMANCE COMPLETION DATE FROM 8/12/25 TO 9/26/25, AND EXTENDS THE ULTIMATE ESTIMATED COMPLETION DATE (CLOSEOUT) FROM 10/12/25 TO 11/26/25 |
| Mar 3, 2025 | 0 | $166.2K | THE AWARD FOR THE KEATING HARDENING PHASE II- DESIGN PROJECT LOCATED IN ROCHESTER, NY FOR THE TOTAL OF $166,178.95 IS FOR THE WORK DESCRIBED IN THE SOW DATED 11/21/24. THE PERIOD OF PERFORMANCE COMPLETION DATE IS 7/30/25. |
Research next steps
- Verify whether remaining options may extend performance beyond the current end date.
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.