THE HANLEY VBA 5TH FLOOR- DESIGN AWARD IN THE AMOUNT OF $99,758.87 FOR THE WORK DESCRIBED IN THE SOW DATED 8/02/24 LOCATED IN SYRACUSE, NY WAS AWARDED TO NKB. THE POP COMPLETION DATE IS 9/2/25.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyGeneral Services Administration
OfficePBS R2 REPAIR AND ALTERATIONS BRANCH
NAICS541310 — Architectural Services
PSCC1AA — ARCHITECT AND ENGINEERING- CONSTRUCTION: OFFICE BUILDINGS
Parent award / vehicle47PC0321D0004
Set-asideSMALL BUSINESS SET ASIDE - TOTAL
Pricing typeFIRM FIXED PRICE
Obligations$115.7K
Current contract value$115.7K
Potential contract value / ceiling$115.7K
Start dateMar 18, 2025
Current end dateNov 6, 2025
Potential end dateJan 6, 2026
Latest award activityOct 10, 2025
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 4 of 4 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Oct 10, 2025PS0003$0THIS TIME EXTENSION MOD FOR THE HANLEY VBA 5TH FLOOR- DESIGN PROJECT IS TO EXTEND THE PERIOD OF PERFORMANCE COMPLETION DATE FROM 10/6/25 TO 11/6/25, AND EXTEND THE ULTIMATE ESTIMATED COMPLETION DATE (CLOSEOUT) FROM 12/6/25 TO 1/6/26
Sep 9, 2025PS0002$16.0KTHE MOD IS TO INCORPORATE THE SOW DATED 8/19/25, REASSIGN THE PROJECT'S COR TO JASON LITZ, INCREASES THE AWARD TOTAL TO $115,727.87, EXTEND THE POP COMPLETION DATE TO 10/6/25, AND EXTEND THE ULTIMATE ESTIMATED COMPLETION DATE FROM 11/2/25 TO 12/6/25
Jul 2, 2025PA0001$0THE PURPOSE OF THIS INTERNAL ADMINISTRATIVE MODIFICATION FOR THE HANLEY VBA 5TH FLOOR- DESIGN CONTRACT IS TO THAT ALL PIV CARDS ISSUED UNDER THIS CONTRACT ARE CONSIDERED GOVERNMENT FURNISHED PROPERTY
Mar 19, 20250$99.8KTHE HANLEY VBA 5TH FLOOR- DESIGN AWARD IN THE AMOUNT OF $99,758.87 FOR THE WORK DESCRIBED IN THE SOW DATED 8/02/24 LOCATED IN SYRACUSE, NY WAS AWARDED TO NKB. THE POP COMPLETION DATE IS 9/2/25.

Research next steps

  1. Verify whether remaining options may extend performance beyond the current end date.
  2. Confirm the ordering vehicle and your eligibility or a qualified teaming route.
  3. Check the stated set-aside against the solicitation and current certifications.
  4. Review the award scope and buyer evidence before making a bid/no-bid decision.