Federal contract award
47PC0225F0013
THE HANLEY VBA 5TH FLOOR- DESIGN AWARD IN THE AMOUNT OF $99,758.87 FOR THE WORK DESCRIBED IN THE SOW DATED 8/02/24 LOCATED IN SYRACUSE, NY WAS AWARDED TO NKB. THE POP COMPLETION DATE IS 9/2/25.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | General Services Administration |
| Office | PBS R2 REPAIR AND ALTERATIONS BRANCH |
| NAICS | 541310 — Architectural Services |
| PSC | C1AA — ARCHITECT AND ENGINEERING- CONSTRUCTION: OFFICE BUILDINGS |
| Parent award / vehicle | 47PC0321D0004 |
| Set-aside | SMALL BUSINESS SET ASIDE - TOTAL |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $115.7K |
| Current contract value | $115.7K |
| Potential contract value / ceiling | $115.7K |
| Start date | Mar 18, 2025 |
| Current end date | Nov 6, 2025 |
| Potential end date | Jan 6, 2026 |
| Latest award activity | Oct 10, 2025 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 4 of 4 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Oct 10, 2025 | PS0003 | $0 | THIS TIME EXTENSION MOD FOR THE HANLEY VBA 5TH FLOOR- DESIGN PROJECT IS TO EXTEND THE PERIOD OF PERFORMANCE COMPLETION DATE FROM 10/6/25 TO 11/6/25, AND EXTEND THE ULTIMATE ESTIMATED COMPLETION DATE (CLOSEOUT) FROM 12/6/25 TO 1/6/26 |
| Sep 9, 2025 | PS0002 | $16.0K | THE MOD IS TO INCORPORATE THE SOW DATED 8/19/25, REASSIGN THE PROJECT'S COR TO JASON LITZ, INCREASES THE AWARD TOTAL TO $115,727.87, EXTEND THE POP COMPLETION DATE TO 10/6/25, AND EXTEND THE ULTIMATE ESTIMATED COMPLETION DATE FROM 11/2/25 TO 12/6/25 |
| Jul 2, 2025 | PA0001 | $0 | THE PURPOSE OF THIS INTERNAL ADMINISTRATIVE MODIFICATION FOR THE HANLEY VBA 5TH FLOOR- DESIGN CONTRACT IS TO THAT ALL PIV CARDS ISSUED UNDER THIS CONTRACT ARE CONSIDERED GOVERNMENT FURNISHED PROPERTY |
| Mar 19, 2025 | 0 | $99.8K | THE HANLEY VBA 5TH FLOOR- DESIGN AWARD IN THE AMOUNT OF $99,758.87 FOR THE WORK DESCRIBED IN THE SOW DATED 8/02/24 LOCATED IN SYRACUSE, NY WAS AWARDED TO NKB. THE POP COMPLETION DATE IS 9/2/25. |
Research next steps
- Verify whether remaining options may extend performance beyond the current end date.
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.