| Field | Reported value |
|---|---|
| Agency | General Services Administration |
| Office | PBS R2 CAPITAL CONSTRUCTION BRANCH |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Y1AA — CONSTRUCTION OF OFFICE BUILDINGS |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $10.6M |
| Current contract value | $10.6M |
| Potential contract value / ceiling | $10.6M |
| Start date | Jun 26, 2023 |
| Current end date | Nov 3, 2025 |
| Potential end date | Oct 30, 2026 |
| Latest award activity | Jul 17, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 38 of 38 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jul 17, 2026 | PS0040 | $0 | NO COST TIME EXTENSION TO COMPLETE WORK IN MODIFICATION 37 |
| Jun 30, 2026 | PS0039 | $0 | INCORPORATING DEI CLAUSE UNDER EO 14398 |
| Jun 1, 2026 | PS0038 | $-78.5K | THE PURPOSE OF THIS MODIFICATION IS TO REMOVE THE REMAINING CREDIT IN THE AMOUNT OF $78,523.80 FOR THE DESCOPED USMS GROUND LEVEL WORK (MOD 7, PA0007). |
| May 12, 2026 | PS0037 | $20.4K | USMS DOOR HARDWARE. |
| May 5, 2026 | PA0035 | $0 | CONTRACT EXTENSION TO 5-31-2026 |
| May 5, 2026 | PA0036 | $-20.4K | DEOBLIGATION (USMS CREDIT): DEOBLIGATE CREDIT FUNDS TO BE USED TO FUND ADDITIONAL WORK STEP 1 OF THE DEOBLIGATION PROCESS, DEOBLIGATE $20,366.33 FROM CLIN 0006 "MOD #5 USMS HOLDING CELL ADJUSTMENT" UNDER PR ACCT. LINE NO. 7 FOR RWA 5015359. |
| Feb 24, 2026 | PC0034 | $0 | TIME EXTENSION TO 3-14-2026 |
| Feb 6, 2026 | PS0033 | $2.7K | DOOR HARDWARE AT THE RESTRICTED CORRIDOR 3-51 ENTRANCE |
| Feb 3, 2026 | PA0032 | $0 | TIME EXTENSION TO 2-28-2026. |
| Jan 6, 2026 | PS0031 | $4.4K | EGRESS SINAGE. |
| Dec 18, 2025 | PA0030 | $0 | ADMIN MOD FOR TIME EXTENSION |
| Dec 15, 2025 | PA0029 | $0 | BOT MOD |
| Oct 20, 2025 | PA0028 | $0 | NO COST TIME MODIFICATION TO 12-31-2025 TO ACCOMODATE IDS FOR PUNCH LIST COMPLETION. |
| Sep 25, 2025 | PS0027 | $4.4K | MOD 17 |
| Sep 11, 2025 | PS0026 | $23.1K | MOD 22- AV FIXTURE MOVEMENT. |
| Aug 19, 2025 | PS0025 | $24.0K | LIGHTING ADJUSTMENT. |
| Jul 22, 2025 | PS0024 | $88.1K | FIRE ALARM MOD |
| Jul 15, 2025 | PS0023 | $22.9K | USMS DOOR HARDWARE PURCHASE AND INSTALLATION. |
| Jul 9, 2025 | PA0022 | $0 | TIME EXTENSION TO NEGOTIATE MODS. |
| Jun 23, 2025 | PS0021 | $13.3K | MOD 18 PLUMBING ADJUSTMENT |
| May 13, 2025 | PS0020 | $2.5K | MOD 16 RAILING HINGES. |
| Apr 22, 2025 | PS0019 | $4.3K | INSTALLATION OF A SECURITY CEILING MODIFICATION. |
| Apr 16, 2025 | PS0018 | $38.0K | MOD 14 FOR ASSORTED AV AND ELECTRICAL MODIFICATIONS. |
| Apr 15, 2025 | PA0017 | $0 | CORRECT END DATE TO 7-10-2025 |
| Apr 1, 2025 | PS0016 | $72.9K | STONE WAINSCOAT |
| Mar 20, 2025 | PS0014 | $3.6K | INSTALLATION OF FLOOR DRAIN. |
| Feb 27, 2025 | PS0013 | $18.9K | REQUEST FOR EQUITABLE ADJUSTMENT FINALIZED. |
| Feb 12, 2025 | PS0012 | $75.1K | MOD #11 - STAIRS, BLINDS, WHEELCHAIR LIFT, JURY BOX PLATFORMS |
| Jan 16, 2025 | PS0011 | $37.1K | MOD #8 - EXHAUST UNIT, BMS, VALVE ACTUATOR REPLACEMENT |
| Dec 12, 2024 | PS0010 | $2.5K | DOOR HARDWARE |
| Sep 11, 2024 | PS0009 | $581.6K | AV MOD |
| Aug 20, 2024 | PS0008 | $250.7K | MOD 0008 |
| Aug 7, 2024 | PA0007 | $0 | ADMINISTRATIVE MODIFICATION CREDIT |
| Jul 1, 2024 | PS0006 | $213.3K | MOD 4 |
| Jun 20, 2024 | PS0005 | $111.1K | MOD #3 UTILITIES CONFLICT RESOLUTION |
| Feb 28, 2024 | PS0004 | $14.1K | THIS IS A DOOR SCHEDULE MODIFICATION. |
| Jul 25, 2023 | PC0003 | $118.0K | EXERCISE OPTION 1 |
| Jul 20, 2023 | 0 | $9.0M | GC FOR 3RD FLOOR REFURBISHMENT OF BRIENT FEDERAL COURTHOUSE IN WHITE PLAINS, NY |
Estimated positioning window
Oct 25, 2026 – Jan 23, 2027
70/100
Why this recompete signal
Contract timing and recorded acquisition signals at the time of calculation.
Stored score: 70/100. Available recorded signals: 65 points.
- Contract end 2026-10-30 (5 days from calculation)
- +35 points
- 5 historical awards in this buyer and category group
- +15 points
- 38 recorded award transactions
- +10 points
- Latest award action: 2026-07-17
- +5 points
- Parent award identifier recorded
- +0 points
- Solicitation identifier recorded
- +0 points
- Linked official forecast
- +0 points
- Calculated on
- 2026-10-25 10:18:04.631876+00:00
The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.
Rule-based research score; it does not measure your chance of winning.
This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.
Recompete score calculated Oct 25, 2026.
Research next steps
- Check the linked forecast or SAM for a confirmed solicitation and current timing.
- Verify whether remaining options may extend performance beyond the current end date.
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.