Federal contract award

47PC0420F0062

JFK CBP CONVEYOR BELT PROJECT

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyGeneral Services Administration
OfficePBS R2 SIMPLIFIED ACQ BR GROUP 1
NAICS236220 — Commercial and Institutional Building Construction
PSCZ2AA — REPAIR OR ALTERATION OF OFFICE BUILDINGS
Parent award / vehicleGS02P14PCD0012
Set-asideSMALL BUSINESS SET ASIDE - TOTAL
Pricing typeFIRM FIXED PRICE
Obligations$2.9M
Current contract value$2.9M
Potential contract value / ceiling$2.9M
Start dateFeb 11, 2020
Current end dateSep 30, 2022
Potential end dateSep 30, 2022
Latest award activityJul 7, 2022
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 14 of 14 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jul 7, 2022PS0014$6.3KREPLACEMENT OF DAMAGED TARP AT JFK IMF
Apr 22, 2022PS0013$14.7KCBP CONVEYOR BELT REMOVAL DESIGN BUILD AT THE INTERNATIONAL MAILING FACILITY
Mar 1, 2022PS0012$0CBP CONVEYOR BELT REMOVAL DESIGN BUILD - NO COST TIME EXTENSION
Aug 26, 2021PS0010$28.9KMOD 10 IS ISSUED TO DESIGN AND CONSTRUCT A PERMANENT ROLL-UP DOOR FOR THE SPACE.
Jul 29, 2021PS0009$0MOD 9 EXTENDS THE CONTRACT COMPLETION DATE FROM JUNE 30, 3031 TO DECEMBER 31, 2021 TO COMPLETE THE CONSTRUCTION.
Mar 9, 2021PA0008$0MODIFICATION ISSUED TO TRANSFER CONTRACT ADMINISTRATION.
Jan 13, 2021PC0007$344.8KJFK CBP CONVEYOR BELT PROJECT MOD NUMBER PC0007 ISSUE FOR ADDITIONAL WORK.
Jan 12, 2021PS0006$17.5KJFK CBP CONVEYOR BELT PROJECT, ADDITIONAL WORK
Dec 3, 2020PS0005$16.3KJFK CBP CONVEYOR BELT MOD NUMBER PS0005
Oct 22, 2020PC0004$59.9KMOD TO INCORPORATE THE RELOCATION OF THE 2 ELECTRICAL PANELS
Sep 22, 2020PC0003$6.0KMODIFICATION TO INCORPORATE ADDITIONAL WORK RELATED TO THE ELECTRIC WORK AT THE SUB PANEL IN POSTAL OFFICE.
Sep 3, 2020PS0002$46.8KMOD NUMBER PC07 ISSUED TO INCORPORATE ADDITIONAL JANITORIAL SERVICES DURING THE 16 WEEK CONSTRUCTION PHASE.
Aug 19, 2020PS0001$77.0KJFK CBP CONVEYOR BELT PROJECT
Feb 11, 20200$2.3MJFK CBP CONVEYOR BELT PROJECT

Research next steps

  1. Confirm the ordering vehicle and your eligibility or a qualified teaming route.
  2. Check the stated set-aside against the solicitation and current certifications.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.