Federal contract award

47PD0123F0001

ARCHITECTURE/ENGINEERING SERVICES TO STUDY THE SSA RMB BUILDING SECURITY AND POWER SYSTEMS. A/E TO PROVIDE A SINGLE LINE WIRE DIAGRAM AS PART OF THE STUDY. THIS WILL BE LOCATED AT WOODLAWN, MD. TASK ORDER COST IS $358,208.56

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyGeneral Services Administration
OfficePBS R3 ACQ MGMT DIV NORTH
NAICS541330 — Engineering Services
PSCC1AA — ARCHITECT AND ENGINEERING- CONSTRUCTION: OFFICE BUILDINGS
Parent award / vehicle47PD0322D0008
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$342.2K
Current contract value$342.2K
Potential contract value / ceiling$342.2K
Start dateOct 20, 2022
Current end dateAug 15, 2025
Potential end dateAug 15, 2025
Latest award activityOct 2, 2025
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 5 of 5 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Oct 2, 2025PA0007$-16.1KTHE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE $16,051.68 DUE TO SERVICES NOT NEEDED TO COMPLETE THIS PROJECT.
Jul 9, 2025PA0006$0SSA WOODLAWN SECURITY SYSTEM SURVEY AND STUDY 6401 SECURITY BOULEVARD, WOODLAWN, MD. THE PURPOSE OF THIS MODIFICATION IS TO CHANGE THE CONTRACT COMPLETION DATE FROM 07/04/2025 TO 08/15/2025.
May 12, 2025PA0005$0THIS A BILATERAL NO COST MODIFICATION IS FOR THE SSA SECURITY SINGLE LINE DIAGRAM STUDY TO EXTEND THE CONTRACT COMPLETION DATE FROM 5/2/25 TO 07/04/2025. THIS IS TO ACCOMMODATE THE FINAL'S SUBMISSION, REVIEW, AND COMPLETION OF THE STUDY.
Apr 2, 2025PA0004$0THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE CONTRACT COMPLETION DATE OF THE SSA SECURITY AND POWER SYSTEM DIAGRAMS STUDY TO MAY 2, 2025
Oct 23, 2024PA0003$0THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE CONTRACT COMPLETION DATE FROM 11/11/2024 TO 01/31/2025 TO ACCOMMODATE THE REMAINING ENGINEERING SERVICES AS INDICATED BY THE SOW.