Federal contract award
47PD0223C0016
CONSTRUCTION CONTRACT TO UPGRADE THE SECURITY ASPECTS OF THE HOFFMAN U.S. COURTHOUSE LOCATED IN NORFOLK, VA.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | General Services Administration |
| Office | PBS R3 ACQ MGMT DIV SOUTH |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Z2AA — REPAIR OR ALTERATION OF OFFICE BUILDINGS |
| Parent award / vehicle | Not reported |
| Set-aside | 8(A) SOLE SOURCE |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $4.9M |
| Current contract value | $4.9M |
| Potential contract value / ceiling | $4.9M |
| Start date | Sep 13, 2023 |
| Current end date | Jun 8, 2026 |
| Potential end date | Aug 8, 2026 |
| Latest award activity | Jul 7, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 11 of 11 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jul 7, 2026 | PS0022 | $0 | DEI MOD |
| Jun 11, 2026 | PS0021 | $0 | IAW GSAM 552.211-70 "SUBSTANTIAL COMPLETION" THE WORK WAS ACCEPTED AS COMPLETE AS OF 6/08/2026. THIS IS A ZERO DOLLAR MODIFICATION, ALL OTHER ITEMS REMAIN UNCHANGED. |
| Apr 28, 2026 | PS0020 | $130.2K | THIS MODIFICATION INCREASES FUNDING TO ADD USMS SECURITY INFRASTRUCTURE/ADDITIONAL SCOPE, SURFACE MOUNTED RUNWAY, 4TH FLOOR, AND REVERSE 1ST FLOOR WEAPONS STORAGE DOOR. THE PERIOD OF PERFORMANCE AND ALL OTHER ITEMS REMAIN UNCHANGED. |
| Apr 6, 2026 | PS0019 | $0 | CONTRACT MODIFICATION EXTENDS THE PERIOD OF PERFORMANCE TO 5/31/2026. THIS IS A ZERO DOLLAR CONTRACT MODIFICATION. ALL OTHER ITEMS REMAIN UNCHANGED. |
| Jan 5, 2026 | PA0018 | $0 | CONTRACT MODIFICATION EXTENDS THE PERIOD OF PERFORMANCE THROUGH 2/02/2026. THIS IS A ZERO DOLLAR MODIFICATION. ALL OTHER ITEMS REMAIN UNCHANGED. |
| Oct 15, 2025 | PS0017 | $27.9K | CONTRACT MODIFICATION PS0017 ADDS FUNDING IN THE AMOUNT OF $27,852.00 FOR MULTIPLE CHANGES TO THE CONTRACT FOR ADDITIONAL WORK WITHIN SCOPE. THE CONTRACT COMPLETION DATE HAS BEEN EXTENDED TO 10/24/2025. ALL OTHER ITEMS REMAIN UNCHANGED. |
| Jul 7, 2025 | PS0016 | $9.1K | CONTRACT MODIFICATION PS16 ADDS FUNDS FOR THE PROCUREMENT OF DOOR PULLS AND THE REMOVAL AND REINSTALLATION OF DOOR CLOSERS AT THE HOFFMAN COURTHOUSE. ALL OTHER ITEMS REMAIN UNCHANGED. |
| Jun 2, 2025 | PS0015 | $7.8K | CONTRACT MODIFICATION ADDS FUNDING TO REMOVAL OF THE EXISTING INSTALLED CONDUIT AND DEVICE CABLES, REROUTING THE CONDUIT AND REPULLING NEW CABLE AND THEN PROVIDING TESTING OF THE AFFECTED INTRUSION DEVICES. ALL OTHER ITEMS REMAIN UNCHANGED. |
| Mar 25, 2025 | PS0014 | $0 | HOFFMAN FB SECURITY UPGRADES CONSTRUCTION, NORFOLK, VA |
| Mar 18, 2025 | PS0013 | $663.3K | CONTRACT MODIFICATION PS0013 ADDS FUNDING IN THE AMOUNT OF $663,257.00 TO ANSWER NUMEROUS RFIS AND TO FIX AN UNDERGROUND PIPE AT THE MAIN ENTRANCE. THE PERIOD OF PERFORMANCE IS EXTENDED TO 9/15/2025. ALL OTHER ITEMS REMAIN UNCHANGED. |
| Nov 14, 2024 | PS0012 | $59.0K | CONTRACT MODIFICATION ADDS $58,357.37 TO RECONCILE RFIS AND UNFORSEEN CONDITIONS. THE PERIOD OF PERFORMANCE HAS BEEN EXTENDED TO 3/01/2025. |
Research next steps
- Verify whether remaining options may extend performance beyond the current end date.
- Check the stated set-aside against the solicitation and current certifications.