Federal contract award

47PD0224C0016

LOADING DOCK REHAB-PHASE 3. JOSEPH F. WEIS JR. COURTHOUSE, 700 GRANT STREET, PITTSBURGH, PA 15219. REPLACE TRENCH DRAINS, SURROUNDING CONCRETE, DETERIORATED STEEL SUPPORT MEMBERS, AND LEAD BASED PAINT.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyGeneral Services Administration
OfficePBS R3 ACQ MGMT DIV SOUTH
NAICS236220 — Commercial and Institutional Building Construction
PSCZ2AA — REPAIR OR ALTERATION OF OFFICE BUILDINGS
Parent award / vehicleNot reported
Set-aside8(A) SOLE SOURCE
Pricing typeFIRM FIXED PRICE
Obligations$2.7M
Current contract value$2.7M
Potential contract value / ceiling$2.7M
Start dateJun 13, 2024
Current end dateMay 1, 2026
Potential end dateMay 31, 2026
Latest award activityApr 23, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 10 of 10 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Apr 23, 2026PA0009$0THIS MODIFICATION IS A FIXED ASSET MODIFICATION TO REFLECT SUBSTANTIAL COMPLETION ACHIEVED.
Nov 25, 2025PS0008$0JOSEPH F. WEIS JR. COURTHOUSE LOADING DOCK REHAB PHASE 3, 700 GRANT STREET PITTSBURGH, PA 15219 PITTSBURGH, PA. THIS MODIFICATION EXTENDS THE THE SUBSTANTIAL COMPLETION DATE TO 5/1/2026, AND THE CONTRACT COMPLETION DATE TO 5/31/2026.
Jun 10, 2025PS0007$194.6KJOSEPH F. WEIS JR. COURTHOUSE LOADING DOCK REHAB PHASE 3, 700 GRANT STREET PITTSBURGH, PA 15219 PITTSBURGH, PA. THIS MODIFICATION INCORPORATES INCORPORATE RFP0006 AND RFP0007
May 16, 2025PS0006$17.3KJOSEPH F. WEIS JR. COURTHOUSE LOADING DOCK REHAB PHASE 3, PITTSBURGH, PA. THIS MODIFICATION INCORPORATES RFP001 REV1 & 2 RFP 004 RFP 005
Mar 26, 2025PS0005$0JOSEPH F. WEIS JR. COURTHOUSE LOADING DOCK REHAB PHASE 3, PITTSBURGH, PA. THIS MODIFICATION IS FOR THE IMPLEMENTATION OF CDS AND DRONES CLAUSE
Mar 14, 2025PS0004$2.9KJOSEPH F. WEIS JR. COURTHOUSE LOADING DOCK REHAB PHASE 3, PITTSBURGH, PA. THIS MODIFICATION IS TO INSTALL TEMPORARY STAIRS ADJACENT TO THE GUARD SHACK.
Sep 10, 2024PS0003$10.6KJOSEPH F. WEIS JR. COURTHOUSE LOADING DOCK REHAB PHASE 3, PITTSBURGH, PA. THIS MODIFICATION IS TO INCORPORATE RFP002 TO CLEAR TREE BRANCHES
Aug 22, 2024PS0002$6.8KJOSEPH F. WEIS JR. COURTHOUSE LOADING DOCK REHAB PHASE 3, PITTSBURGH, PA. THIS MODIFICATION IS TO ADD FOR IRA CONSTRUCTION SIGNAGE.
Jul 8, 2024PS0001$0NOTICE TO PROCEED LOADING DOCK REHAB-PHASE 3. JOSEPH F. WEIS JR. COURTHOUSE, 700 GRANT STREET, PITTSBURGH, PA 15219.
Jun 13, 20240$2.4MLOADING DOCK REHAB-PHASE 3. JOSEPH F. WEIS JR. COURTHOUSE, 700 GRANT STREET, PITTSBURGH, PA 15219. REPLACE TRENCH DRAINS, SURROUNDING CONCRETE, DETERIORATED STEEL SUPPORT MEMBERS, AND LEAD BASED PAINT.

Research next steps

  1. Verify whether remaining options may extend performance beyond the current end date.
  2. Check the stated set-aside against the solicitation and current certifications.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.