Federal contract award

47PD0224C0020

NIXS FCU REPLACEMENT CONSTRUCTION PHASE 1, ROBERT C NIXS FEDERAL BUILDING, PHILADELPHIA PA. THIS AWARD IS FOR PHASE 1 CONSTRUCTION TO REPLACE FAN COIL UNITS.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyGeneral Services Administration
OfficePBS R3 ACQ MGMT DIV SOUTH
NAICS236220 — Commercial and Institutional Building Construction
PSCZ2AA — REPAIR OR ALTERATION OF OFFICE BUILDINGS
Parent award / vehicleNot reported
Set-aside8(A) SOLE SOURCE
Pricing typeFIRM FIXED PRICE
Obligations$3.0M
Current contract value$3.0M
Potential contract value / ceiling$3.0M
Start dateJul 19, 2024
Current end dateJun 1, 2026
Potential end dateJul 1, 2026
Latest award activityMar 9, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 7 of 7 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Mar 9, 2026PS0009$0THIS MODIFICATION UPDATES THE SUBSTANTIAL AND ULTIMATE COMPLETION DATE TO ALLOW G-FORCE TO UPDATE LOCAL CONTROLS. THE DATES ARE CHANGED FROM 1/30/26 TO 6/1/26, AND FROM 2/27/26 TO 7/1/26
Feb 4, 2026PA0008$0ADMINISTRATIVE MODIFICATION TO REVERSE SUBSTANTIAL COMPLETION FIXED ASSET RECORDING DONE BY IN ERROR FOR THE PHASE 1 NIX FAN COIL REPLACEMENT, AT THE R.C. NIX FEDERAL BUILDING, PHILA, PA
Jan 12, 2026PS0007$42.4KTHIS MOD UPDATES THE COMPLETION DATE FROM 10/30/25 TO 1/30/26, AND THE ULTIMATE DATE TO 2/27/26. ADDITONALLY, THIS WORK COVERS CONSTRUCTIONS SERVICES FOR THE NIX COURTHOUSE BUILDING IN PLHA, PA.
Jul 15, 2025PS0006$28.2KNIXS FCU REPLACEMENT PHASE 1, ROBERT C. NIXS FEDERAL BUILDING, PHILADELPHIA, PA. THIS MODIFICATION INCORPORATES THE INSTALLATION OF ACCESS PANELS FOR JUDGES OFFICES.
May 20, 2025PS0005$0NIXS FCU REPLACEMENT PROJECT, ROBERT C. NIXS FEDERAL BUILDING, PHILADELPHIA, PA. THIS MODIFICATION INCORPORATES IMPLEMENTATION OF CLASS DEVIATIONS AND DRONES CLAUSE.
Feb 27, 2025PS0004$25.0KNIXS FCU REPLACEMENT PROJECT, ROBERT C. NIXS FEDERAL BUILDING, PHILADELPHIA, PA. THIS MODIFICATION INCORPORATES USE OF THE FREEZE METHOD.
Nov 19, 2024PS0003$47.0KNIXS FCU REPLACEMENT PROJECT, ROBERT C. NIXS FEDERAL BUILDING, PHILADELPHIA, PA. THIS MODIFICATION INCORPORATES REPLACEMENT OF THE RISER VALVES.

Research next steps

  1. Verify whether remaining options may extend performance beyond the current end date.
  2. Check the stated set-aside against the solicitation and current certifications.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.