Federal contract award
47PD0224F0050
BYRNE-GREEN TRUCK YARD CONCRETE REPLACEMENT CONSTRUCTION PROJECT. BYRNE GREEN FEDERAL BUILDING, 600 ARCH ST, PHILADELPHIA, PA. THIS PROJECT REPLACE THE EXISTING CONCRETE OF THE TRUCK YARD.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | General Services Administration |
| Office | PBS R3 ACQ MGMT DIV SOUTH |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Z2AA — REPAIR OR ALTERATION OF OFFICE BUILDINGS |
| Parent award / vehicle | 47PD0223D0001 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $3.5M |
| Current contract value | $3.5M |
| Potential contract value / ceiling | $3.5M |
| Start date | Jul 12, 2024 |
| Current end date | Sep 1, 2025 |
| Potential end date | Oct 31, 2025 |
| Latest award activity | Oct 30, 2025 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 8 of 8 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Oct 30, 2025 | PA0011 | $0 | ADMINISTRATIVE MOD TO CORRECT THE FIXED ASSET LINE IN THE ACCOUNTING STRING |
| Sep 17, 2025 | PA0009 | $0 | BYRNE GREEN TRUCK YARD CONCRETE REPLACEMENT, PHILADELPHIA, PA. THIS IS AN ADMINISTRATIVE MODIFICATION TO CORRECT THE FIXED ASSET LINES OF ACCOUNTING |
| Aug 7, 2025 | PS0008 | $7.5K | BYRNE GREEN TRUCK YARD CONCRETE REPAIR - BYRNE GREEN FEDERAL BUILDING, PHILADELPHIA, PA. THIS MODIFICATION INCORPORATES UNFORESEEN SOFFIT REPAIRS TO THE TRUCK YARD |
| May 8, 2025 | PS0007 | $41.5K | BYRNE GREEN TRUCK YARD CONCRETE REPLACEMENT, BYRNE GREEN FEDERAL BUILDING, PHILADELPHIA, PA. UPDATING IRA SIGN FOR NEW ADMIN AND ADDITIONAL CONCRETE WORK FOR PHASES 1 AND 2 WITH FLOWABLE FILL. |
| Mar 17, 2025 | PS0006 | $67.5K | BYRNE GREEN TRUCK YARD CONCRETE REPLACEMENT, BYRNE GREEN FEDERAL BUILDING, PHILADELPHIA, PA. MODIFICATION TO ADD ADDITIONAL REBAR AND CONCRETE POUR TO SATISFY RFP 06 REQUIREMENTS |
| Mar 6, 2025 | PS0005 | $27.8K | BYRNE GREEN TRUCK YARD CONCRETE REPLACEMENT PROJECT, BYRNE GREEN FEDERAL BUILDING, PHILADELPHIA, PA. MOD FOR ADDITIONAL WORK FOR C-CHANNEL STEEL REPLACEMENT AND OTHER STEEL WORK ALONG THE DOCK |
| Feb 10, 2025 | PS0004 | $60.0K | BYRNE GREEN TRUCK YARD MODIFICATION RFP 06 - PHILADELPHIA, PA - MOD TO REMOVE UNFORESEEN PIPE FOUND DURING DEMO WITH HAZARD FLUID INSIDE. |
| Dec 17, 2024 | PS0002 | $59.7K | BYRNE GREEN TRUCKYARD CONCRETE REPLACEMENT - BYRNE GREEN FEDERAL BUILDING, PHILADELPHIA, PA. MODIFICATION TO ADD REBAR TO THE SLOPED AREA PREVIOUSLY UNDISCOVERED IN DRAWINGS. |
Research next steps
- Verify whether remaining options may extend performance beyond the current end date.
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.