Federal contract award
47PD5226F0091
CORRECT/ADD DUCTWORK FOR THE 6TH FLOOR, REPLACE THE 3 WAY 6-INCH CONDENSER WATER VALVE AND UPGRADE THE BOILER GAS PRESSURE REGULATOR R.C. WHITE TX0272 EL PASO, TEXAS 79901
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | General Services Administration |
| Office | PBS PROJECT DELIVERY WEST - BRANCH B |
| NAICS | 561210 — Facilities Support Services |
| PSC | Z1AA — MAINTENANCE OF OFFICE BUILDINGS |
| Parent award / vehicle | 47PH0223D0003 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $107.0K |
| Current contract value | $107.0K |
| Potential contract value / ceiling | $107.0K |
| Start date | Feb 17, 2026 |
| Current end date | Sep 30, 2026 |
| Potential end date | Sep 30, 2026 |
| Latest award activity | Aug 13, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 2 of 2 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Aug 13, 2026 | PC0002 | $58.2K | THE PURPOSE OF THIS MODIFICATION IS TO ADD ADDITIONAL FUNDING IN THE AMOUNT OF $58,170.87 MAKING THE TOTAL AWARD FOR THIS PROCURMENT NOW BE $107,032.87. THE INCREASE IS DUE TO ADDITONAL DUCT WORK WAS REQUIRED. |
| Feb 25, 2026 | 0 | $48.9K | CORRECT/ADD DUCTWORK FOR THE 6TH FLOOR, REPLACE THE 3 WAY 6-INCH CONDENSER WATER VALVE AND UPGRADE THE BOILER GAS PRESSURE REGULATOR R.C. WHITE TX0272 EL PASO, TEXAS 79901 |