Federal contract award

47PE5426F0280

REPAIR CONDUIT FROM BELOW CEILING AND INSTALL NEW CONDUIT FROM EXISTING FUSE BUCKET TO THE LINE SIDE OF THE CONTROL PANEL. REPAIR LEAK IN HOT WATER PIPE ON THE 42ND FLOOR AT JCK FEDERAL BUILDING IL0236FC 230 S. DEARBORN ST. CHICAGO, IL 60604

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyGeneral Services Administration
OfficePBS PROJECT DELIVERY CENTRAL - BRANCH D
NAICS561210 — Facilities Support Services
PSCZ1AA — MAINTENANCE OF OFFICE BUILDINGS
Parent award / vehicle47PF0022A0012
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$12.4K
Current contract value$12.4K
Potential contract value / ceiling$12.4K
Start dateJul 7, 2026
Current end dateSep 30, 2026
Potential end dateSep 30, 2026
Latest award activityJul 7, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 1 of 1 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jul 7, 20260$12.4KREPAIR CONDUIT FROM BELOW CEILING AND INSTALL NEW CONDUIT FROM EXISTING FUSE BUCKET TO THE LINE SIDE OF THE CONTROL PANEL. REPAIR LEAK IN HOT WATER PIPE ON THE 42ND FLOOR AT JCK FEDERAL BUILDING IL0236FC 230 S. DEARBORN ST. CHICAGO, IL 60604