ARCHITECT ENGINEER, ELEVAR DESIGN GROUP, INC., AS DESCRIBED IN DESIGN WORK ORDER EDG409, TO REPLACE CHILLED-WATER CIRCULATION PUMPS, AND INSTALL BYPASS LOOP PIPING SYSTEM, AT THE PECK FEDERAL BUILDING, 550 MAIN STREET, CINCINNATI, OHIO 45202.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | General Services Administration |
| Office | PBS R5 ACQUISITION MANAGEMENT DIVISION |
| NAICS | 541310 — Architectural Services |
| PSC | C1AA — ARCHITECT AND ENGINEERING- CONSTRUCTION: OFFICE BUILDINGS |
| Parent award / vehicle | GS05P17SCD0005 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $43.2K |
| Current contract value | $43.2K |
| Potential contract value / ceiling | $43.2K |
| Start date | Aug 20, 2021 |
| Current end date | Aug 31, 2026 |
| Potential end date | Aug 31, 2026 |
| Latest award activity | Mar 4, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 3 of 3 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Mar 4, 2026 | PS0011 | $0 | JOHN WELD PECK FEDERAL OFFICE BUILDING, 550 MAIN STREET, CINCINNATI, OH 45202 AS A RESULT OF THIS MODIFICATION, THE TASK ORDER COMPLETION DATE IS EXTENDED FROM 2/27/2026 TO 8/31/2026 TO MATCH CONSTRUCTION DURATION. |
| Jan 13, 2026 | PS0010 | $0 | JOHN WELD PECK FEDERAL OFFICE BUILDING, 550 MAIN STREET, CINCINNATI, OH THIS MOD IS ISSUED TO EXTEND THE TASK ORDER COMPLETION DATE TO ALLOW THE AE TO PERFORM PCCS, CM&I, AND RECORD DOCUMENT SERVICES DURING THE CONSTRUCTION PHASE OF THE PROJECT. |
| May 9, 2025 | PS0009 | $12.2K | JOHN WELD PECK FEDERAL OFFICE BUILDING, 550 MAIN STREET, CINCINNATI, OH 45202. ACCORDING TO FAR 2.243-1 CHANGES, THIS MODIFICATION ADDS WORK WITHIN SCOPE. |