Federal contract award

47PF0024F0472

47PF0024F0472 RA AND SA MOTOR CONTROLS PROJECT AT THE PECK FB 550 MAIN STREET CINCINNATI, OHIO 45202-3222. THE FOLLOWING IN INCORPORATED BY REFERENCE: R.J. RUNGE PROPOSAL FOR $1,319,000.00.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyGeneral Services Administration
OfficePBS R5 ACQUISITION MANAGEMENT DIVISION
NAICS236220 — Commercial and Institutional Building Construction
PSCZ2AA — REPAIR OR ALTERATION OF OFFICE BUILDINGS
Parent award / vehicle47PF0018D0076
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$1.9M
Current contract value$1.9M
Potential contract value / ceiling$1.9M
Start dateMar 27, 2024
Current end dateJun 19, 2026
Potential end dateJul 20, 2026
Latest award activityJul 16, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 10 of 10 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jul 16, 2026PS0009$-21.5KMODIFICATION ADDS A CREDIT BACK TO THE GOVERNMENT FOR WORK WITHIN SCOPE.CONSTRUCTION SERVICES FOR THE RA AND SA MOTOR CONTROLS PROJECT AT THE JOHN WELD PECK FEDERAL BUILDING, 550 MAIN STREET, CINCINNATI, OHIO 45202-3222.
May 19, 2026PS0008$65.6KMODIFICATION ADDS WORK WITHIN SCOPE DUE TO UNFORESEEN SITE CONDITIONS.CONSTRUCTION SERVICES FOR THE RA AND SA MOTOR CONTROLS PROJECT AT THE JOHN WELD PECK FEDERAL BUILDING, 550 MAIN STREET, CINCINNATI, OHIO 45202-3222.
Mar 4, 2026PS0007$42.4KCONSTRUCTION SERVICE FOR THE RA AND SA MOTOR CONTROLS PROJECT AT THE JOHN WELD PECK FEDERAL BUILDING, 550 MAIN STREET, CINCINNATI, OHIO 45202-3222. THIS MODIFICATION ADDS WORK WITHIN SCOPE DUE TO UNFORESEEN SITE CONDITIONS.
Dec 9, 2025PS0006$341.8KCONSTRUCTION SERVICE FOR THE RA AND SA MOTOR CONTROLS PROJECT AT THE JOHN WELD PECK FEDERAL BUILDING, 550 MAIN STREET, CINCINNATI, OHIO 45202-3222. THIS MODIFICATION ADDS WORK WITHIN SCOPE DUE TO UNFORESEEN SITE CONDITIONS AND EXTENDS COMPLETION.
Feb 27, 2025PS0005$12.9KCONSTRUCTION SERVICES FOR THE RA AND SA MOTOR CONTROLS PROJECT AT THE JOHN WELD PECK FEDERAL BUILDING, 550 MAIN STREET, CINCINNATI, OHIO 45202-3222. THIS MODIFICATION ADDS ADDITIONAL SCOPE AND EXTENDS THE COMPLETION DATE.
Nov 18, 2024PA0004$0THIS MOD IS TO UPDATE THE FUNDING FIXED ASSET ROH11219OH0189CN INFORMATION FROM CIPIMP TO IMPROVMNT IN THE ACCOUNTING LINES OF THIS AWARD. THIS IS AN ADMINISTRATIVE CHANGE TO THE ACCOUNTING ONLY, ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME.
Aug 30, 2024PS0003$15.5KCONTRACT 47PF0018D0076 TASK ORDER 47PF0024F0472 RA AND SA MOTOR CONTROLS PROJECT AT THE PECK FEDERAL BUILDING 550 MAIN STREET CINCINNATI, OH 45202, MODIFICATION PS003 FOR THE WALL FIX.
Jun 20, 2024PS0002$68.0KRA AND SA MOTOR CONTROLS PROJECT AT THE PECK FB 550 MAIN ST. CINCINNATI, OH 45202. WORK INCLUDES: SIX (6) ADDITIONAL COILS NOT SHOWN ON COIL SCHEDULE. CONTRACT COST INCREASED FROM $1,342,808.00 TO $1,410,808.00. CONTRACT COMPLETION REMAINS THE SAME.
May 9, 2024PS0001$23.8KCONTRACT 47PF0018D0076 TASK ORDER 47PF0024F0472 RA AND SA MOTOR CONTROLS PROJECT AT THE PECK FEDERAL BUILDING 550 MAIN STREET CINCINNATI, OH 45202. CONTRACT COST INCREASED FROM $1,319,000.00 TO $1,342,808.00. CONTRACT COMPLETION REMAINS THE SAME.
Mar 27, 20240$1.3M47PF0024F0472 RA AND SA MOTOR CONTROLS PROJECT AT THE PECK FB 550 MAIN STREET CINCINNATI, OHIO 45202-3222. THE FOLLOWING IN INCORPORATED BY REFERENCE: R.J. RUNGE PROPOSAL FOR $1,319,000.00.

Research next steps

  1. Verify whether remaining options may extend performance beyond the current end date.
  2. Confirm the ordering vehicle and your eligibility or a qualified teaming route.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.