Federal contract award
47PF0025F0366
AWARD FOR GIGNOUX COURTHOUSE EXISTING AREA-WAY REPAIR PROJECT AT GIGNOUX U.S. COURTHOUSE,156 FEDERAL STREET PORTLAND, MAINE. PERIOD OF PERFORMANCE IS 90 DAYS FROM NOTICE TO PROCEED.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | General Services Administration |
| Office | PBS R5 ACQUISITION MANAGEMENT DIVISION |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Z1AA — MAINTENANCE OF OFFICE BUILDINGS |
| Parent award / vehicle | 47PB0023D0013 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $263.6K |
| Current contract value | $263.6K |
| Potential contract value / ceiling | $263.6K |
| Start date | Apr 9, 2025 |
| Current end date | Oct 13, 2025 |
| Potential end date | Nov 12, 2025 |
| Latest award activity | Aug 14, 2025 |
| Source loaded | Aug 15, 2026 |
Funding and modification history
Showing the latest 3 of 3 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Aug 14, 2025 | PS0002 | $15.6K | MODIFICATION PS0002 FOR GIGNOUX COURTHOUSE EXISTING AREA-WAY REPAIR PROJECT AT GIGNOUX U.S. COURTHOUSE, 156 FEDERAL STREET PORTLAND, MAINE. PROVIDES SHORING FOR BRICK WALL IN AMOUNT OF $15,604.89. PERIOD OF PERFORMANCE REMAINS 10/13/2025. |
| Jul 10, 2025 | PS0001 | $0 | NOTICE TO PROCEED FOR GIGNOUX COURTHOUSE EXISTING AREA-WAY REPAIR PROJECT AT GIGNOUX U.S. COURTHOUSE, 156 FEDERAL STREET PORTLAND, MAINE. PERIOD OF PERFORMANCE IS SET FOR 7/15/2025 TO 10/13/2025. |
| Apr 9, 2025 | 0 | $248.0K | AWARD FOR GIGNOUX COURTHOUSE EXISTING AREA-WAY REPAIR PROJECT AT GIGNOUX U.S. COURTHOUSE,156 FEDERAL STREET PORTLAND, MAINE. PERIOD OF PERFORMANCE IS 90 DAYS FROM NOTICE TO PROCEED. |
Research next steps
- Verify whether remaining options may extend performance beyond the current end date.
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.