Federal contract award

47PF0025F0866

REPAIR CONCRETE SPILLWAY PARKING LOT 4, HDI FEDERAL CENTER, BATTLE CREEK, MI THE PURPOSE OF THIS PROJECT IS TO SEAL JOINTS AND CRACKS IN THE ASPHALT PARKING LOT TO CONCRETE CURBING, REMOVE AND REPLACE RETAINING BLOCKS, BACKFILL, REGRADE AND SEED.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyGeneral Services Administration
OfficePBS R5 ACQUISITION MANAGEMENT DIVISION
NAICS561210 — Facilities Support Services
PSCZ2QA — REPAIR OR ALTERATION OF RESTORATION OF REAL PROPERTY (PUBLIC OR PRIVATE)
Parent award / vehicle47PF0024A0005
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$26.4K
Current contract value$26.4K
Potential contract value / ceiling$26.4K
Start dateSep 25, 2025
Current end dateJun 22, 2026
Potential end dateAug 21, 2026
Latest award activityDec 8, 2025
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 3 of 3 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Dec 8, 2025PS0002$0MOD PS0002, REPAIR CONCRETE SPILLWAY PARKING LOT 4, HDI FEDERAL CENTER, BATTLE CREEK, MI THE PURPOSE OF THIS MODIFICATION IS TO CAPTURE CHANGES IN TECHNICAL SPECIFICATIONS: 2-PART COLD PATCH ASPHALT WAS USED IN LIEU OF BACKER ROD AND SEALANT.
Oct 30, 2025PS0001$4.4KREPAIR CONCRETE SPILLWAY PARKING LOT 4, HDI FEDERAL CENTER, BATTLE CREEK, MI THE PURPOSE OF THIS MODIFICATION IS TO REMOVE AND REPLACE CONCRETE APRON IN LIEU OF SEALANT.
Sep 25, 20250$22.0KREPAIR CONCRETE SPILLWAY PARKING LOT 4, HDI FEDERAL CENTER, BATTLE CREEK, MI THE PURPOSE OF THIS PROJECT IS TO SEAL JOINTS AND CRACKS IN THE ASPHALT PARKING LOT TO CONCRETE CURBING, REMOVE AND REPLACE RETAINING BLOCKS, BACKFILL, REGRADE AND SEED.

Research next steps

  1. Verify whether remaining options may extend performance beyond the current end date.
  2. Confirm the ordering vehicle and your eligibility or a qualified teaming route.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.