Federal contract award
47PH0822F0016
CONSTRUCTION OF A NEW US COURTHOUSE IN GREENVILLE, MS
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | General Services Administration |
| Office | PBS R7 PROG SUPPORT - CAPITAL AND IDIQ |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Z2AA — REPAIR OR ALTERATION OF OFFICE BUILDINGS |
| Parent award / vehicle | 47PH0821D0009 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $49.6M |
| Current contract value | $49.6M |
| Potential contract value / ceiling | $49.6M |
| Start date | Mar 29, 2022 |
| Current end date | Mar 27, 2026 |
| Potential end date | Jun 25, 2026 |
| Latest award activity | May 14, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 17 of 17 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 14, 2026 | PC0033 | $0 | THIS MODIFICATION DEFINITIZES PDL MODIFICATION PC0027. THE SCOPE OF WORK TO BE PERFORMED WAS TO INSTALL SMOKE DETECTORS IN THE ELEVATOR PITS AT THE CONSTRUCTION PROJECT. |
| May 13, 2026 | PC0032 | $40.0K | MODIFICATION PC0032 IS FOR WORK NECESSARY TO COMPLETE THE CONSTRUCTION OF THE NEW U. S. COURTHOUSE IN GREENVILLE, MS AS IT PERTAINS TO ADDITIONAL HARDWARE FOR MEANS OF EGRESS AND SECURITY FUNCTIONALITY. |
| Apr 23, 2026 | PC0031 | $-805 | THIS MOD DEFINITIZES MOD PC0030 PDL FOR DUCT DETECTORS AND SMOKE BEAM WORK IN THE GREENVILLE COURTHOUSE, MS. |
| Mar 17, 2026 | PC0030 | $55.3K | PDL MOD TO PROVIDE ALL LABOR, MATERIALS, EQUIPMENT, TRANSPORTATION, AND SUPERVISION NECESSARY TO PERFORM THE WORK IN BULLETIN 36 REVISED (WORK ASSOCIATED WITH LOBBY BEAN DETECTOR RELOCATION) AND BULLETIN 40 (DUCT DETECTORS) |
| Feb 10, 2026 | PC0029 | $196.5K | DEFINITIZE PDL MOD PC0026 FOR BULLETIN 37 SCOPE REQUIREMENTS |
| Feb 2, 2026 | PC0028 | $174.4K | THE WORK INCLUDES CLEANING AFTER INTERIOR AND EXTERIOR WORK, CIVIL, CONCRETE AND SOD WORK, LOWERING THE GATES, INSTALL OF METAL HANDRAILS, CARPENTRY, METAL SHELVING, PAINTING, PLUMBING, ELECTRICAL WORK, AND LABOR FOR INSTALLING NETWORK SWITCHES. |
| Jan 27, 2026 | PC0027 | $52.9K | ADD SMOKE DETECTORS TO THE ELEVATOR PITS |
| Dec 11, 2025 | PC0026 | $244.3K | PARTIAL SOW TO BE PERFORMED FROM BULLETIN 37 RELATED TO ROOFING, DOORS AND HARDWARE (DOORS 246 AND 255), MECHANICAL WORK AND ELECTRICAL WORK |
| Sep 25, 2025 | PC0025 | $107.7K | REMOVAL OF PLYWOOD AND INSTALLATION OF GYPSUM BOARD EXTENDING 1 INCH TO 7 INCH DOWN FROM THE SOFFITS AT THE PERIMETER OF 2ND AND 3RD FLOOR COURTROOMS FOLLOWING PARTIAL REMOVAL OF SLATS. |
| Sep 17, 2025 | PC0024 | $134.3K | MODIFICATION TO ADD VARIOUS PCOS 27 -31, 33-34, AND 37 CONSTRUCTION SIGNAGE, GREENVILLE, MS |
| Aug 13, 2025 | PC0023 | $286.2K | ADD VARIOUS PROPOSED CHANGES AS IT RELATES TO BULLETIN 36, GREENVILLE COURTHOUSE, GREENVILLE, MS |
| Jul 24, 2025 | PC0022 | $386.0K | ADD BULLETIN 35 FOR COURT EAGLE SIGNAGE, EXTERIOR EMBLEM PCO 27 BULLETIN 35 SIGNAGE CHANGE, SWITCHES AND USDC AV, AND ELEVATOR A.17 REQUIREMENTS RFI 741, ETC TO THE SCOPE OF WORK TO BE PERFORMED. |
| Jun 26, 2025 | PC0021 | $72.8K | ADD PCO 032 OVERHEAD DOOR REQUIREMENT, GREENVILLE, MS COURTHOUSE |
| Jun 17, 2025 | PC0020 | $246.4K | PROVIDE CONSTRUCTION EFFORT REQUIRED TO INCORPORATE THE CUSTOM FENCE CORRUGATED PANELS, ELECTRICAL CHANGES RELATED TO RFI-564, RFI-565, RFI-594, RFI-604, RFI-644, RFI-662 AND BULLETIN 30 (PCO 046), AND PATCHING AT HVAC DAMPER CONTROL. |
| Mar 25, 2025 | PC0019 | $0 | NO COST TIME EXTENSION OF CONTRACT FOR THE NEW US COURTHOUSE IN GREENVILLE, MS. |
| Dec 20, 2024 | PS0018 | $246.4K | BULLETIN 34 (MISCELLANEOUS CHANGES) & STRUCTURED CABLING CLARIFICATIONS FOR THE NEW US COURTHOUSE IN GREENVILLE, MS |
| Dec 4, 2024 | PC0017 | $0 | NO COST TIME EXTENSION OF CONTRACT TO 06/26/2025 FOR THE NEW US COURTHOUSE IN GREENVILLE, MS. |
Research next steps
- Verify whether remaining options may extend performance beyond the current end date.
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.