Federal contract award
47PK0624P0010
DIGITAL TECHNOLOGIES ARE TO PROVIDE LABOR AND MATERIAL TO CONSTRUCT DOUBLE DOORS AND BUILD NEW HALLWAY FOR USDC AT THE RONALD REAGAN FEDERAL COURTHOUSE LOCATED AT 411 W. 4TH STREET IN SANTA ANA, CA 92701.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | General Services Administration |
| Office | PBS R9 AMD SAT LOS ANGELES SUPPORT SECTION |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Z2AA — REPAIR OR ALTERATION OF OFFICE BUILDINGS |
| Parent award / vehicle | Not reported |
| Set-aside | 8(A) SOLE SOURCE |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $114.0K |
| Current contract value | $114.0K |
| Potential contract value / ceiling | $114.0K |
| Start date | Jun 20, 2024 |
| Current end date | Mar 31, 2026 |
| Potential end date | Mar 31, 2026 |
| Latest award activity | Dec 12, 2025 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 6 of 6 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Dec 12, 2025 | PS0006 | $0 | THE PURPOSE OF THIS MODIFICATION PS0006 IS TO PROVIDE A NO-COST TIME EXTENSION OF 117 DAYS DAYS FROM THURSDAY DECEMBER 4, 2025 TO TUESDAY MARCH 31, 2026. |
| Sep 29, 2025 | PS0005 | $0 | THE PURPOSE OF THIS MODIFICATION PS0005 IS TO PROVIDE A NO-COST TIME EXTENSION OF 65 DAYS DAYS FROM TUESDAY SEPTEMBER 30, 2025 TO THURSDAY DECEMBER 4, 2025 AT RONALD REAGAN COURTHOUSE CA0295ZZ |
| Apr 30, 2025 | PS0004 | $0 | THE PURPOSE OF THIS MODIFICATION PS0004 IS TO PROVIDE A NO-COST TIME EXTENSION OF 153 DAYS FROM WEDNESDAY APRIL 30, 2025 TO TUESDAY SEPTEMBER 30, 2025 AT RONALD REAGAN COURTHOUSE CA0295ZZ IN SANTA ANA, CA 92701. |
| Apr 22, 2025 | PS0003 | $0 | IMPLEMENTATION OF CDS AND DRONES CLAUSE. NO CHANGE IN PRICE, COMPLETION DATE REMAINS 4/30/2025 AT RONALD REAGAN COURTHOUSE IN SANTA ANA, CA CA0295ZZ. |
| Jan 10, 2025 | PS0002 | $0 | THE PURPOSE OF THIS MODIFICATION PS0002 IS TO PROVIDE A NO-COST TIME EXTENSION OF 110 DAYS FROM THE CURRENT COMPLETION DATE OF JANUARY 10, 2025 TO APRIL 30, 2025. |
| Oct 11, 2024 | PS0001 | $0 | THE PURPOSE OF THIS MOD PS0001 IS TO PROVIDE A NO-COST TIME EXTENSION OF 92 DAYS FROM 10/10/2024 TO 1/10/2025 TO COMPLETE THE PROJECT. THE CONTRACT TOTAL OF $113,988.62 REMAINS UNCHANGED AT RONALD REAGAN FED BLDG CA0295ZZ IN SANTA ANA, CA 92701 |
Research next steps
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.