Federal contract award
47PK1724F0004
AWARD OF THE DESIGN/BUILD CONSTRUCTION OF THE APPRAISERS BLDG ELEVATOR MOD PROJECT LOCATED AT 630 SANSOME STREET, SF, CA. THE SUBSTANTIAL COMPLETION IS DUE 520 CALENDAR DAYS AFTER AWARD.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | General Services Administration |
| Office | PBS R9 AMD FIELD PROJECTS |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Y1AZ — CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS |
| Parent award / vehicle | 47PK0121D0020 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $2.6M |
| Current contract value | $2.6M |
| Potential contract value / ceiling | $2.6M |
| Start date | Oct 11, 2023 |
| Current end date | Sep 22, 2026 |
| Potential end date | Sep 22, 2026 |
| Latest award activity | Oct 10, 2025 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 9 of 9 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Oct 10, 2025 | PA0008 | $0 | UPDATE THE FUNDING FIXED ASSET RCA50494CA0091AA INFORMATION FROM CIPIMP TO IMPROVMNT IN THE ACCOUNTING LINES. |
| Oct 6, 2025 | PS0007 | $0 | NO COST TIME EXTENSION |
| Sep 4, 2025 | PS0006 | $0 | TIME EXTENSION DUE TO PLEXIGLASS INSTALLATION DELAY |
| Jun 23, 2025 | PS0005 | $7.9K | O&M SUPPORT |
| Mar 13, 2025 | PS0004 | $1.3K | ADDITIONAL WORK FOR FIRE SUPPRESSION |
| Feb 6, 2025 | PS0003 | $10.5K | PS0003 - ADDITIONAL SUPERVISION HOURS AND SUPPORT FOR SWITCHGEAR INSTALLATION |
| Aug 9, 2024 | PS0002 | $114.1K | MODIFICATION TO INCORPORATE WITHIN SCOPE CHANGES ON THE DB APPRAISERS BLDG ELEVATOR MOD PROJECT LOCATED IN SF, CA. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED AND IN FULL EFFECT. |
| Dec 6, 2023 | PS0001 | $0 | MODIFICATION TO INCORPORATE THE NOTICE TO PROCEED BASE SCHEDULE FOR THE APPRAISERS BLDG ELEVATOR MODERNIZATION PROJECT LOCATED IN SF, CA |
| Oct 11, 2023 | 0 | $2.5M | AWARD OF THE DESIGN/BUILD CONSTRUCTION OF THE APPRAISERS BLDG ELEVATOR MOD PROJECT LOCATED AT 630 SANSOME STREET, SF, CA. THE SUBSTANTIAL COMPLETION IS DUE 520 CALENDAR DAYS AFTER AWARD. |
Research next steps
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.