TASK ORDER AWARD OF THE DB SANSOME ST ROOF PROJECT LOCATED IN SF, CA. THE TOTAL PERIOD OF PERFORMANCE IS 324 CD AFTER NOTICE TO PROCEED.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyGeneral Services Administration
OfficePBS R9 AMD FIELD PROJECTS
NAICS236220 — Commercial and Institutional Building Construction
PSCY1AZ — CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS
Parent award / vehicle47PK0121D0020
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$2.2M
Current contract value$2.2M
Potential contract value / ceiling$2.2M
Start dateSep 12, 2024
Current end dateSep 24, 2025
Potential end dateOct 24, 2025
Latest award activityAug 8, 2025
Source loadedAug 15, 2026

Funding and modification history

Showing the latest 7 of 7 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Aug 8, 2025PS0007$102.8KPS0007 INCORPORATES MODIFICATION OF PLUMBING TO PRESERVE ROOF FINISH AND WATERPROOFING OF ROOF ANCHORS FOR SANSOME FEDERAL BUILDING, 630 SANSOME ST., SAN FRANCISCO, CA.
Jun 17, 2025PS0006$58.8KPS0006 TO PROVIDE ADDITIONAL OFF-SITE STORAGE, UNFORSEEN DEMO OF SECOND LAYER OF ROOFING AND FIXING WOOD ROT FOR SANSOME ROOF PROJECT AT 630 SANSOME ST. SAN FRANCISCO, CA 94111.
Apr 16, 2025PS0005$13.3KPS0005 ADDS OFF-SITE STORAGE TO SUPPORT THE ROOFING PROJECT AT U.S. APPRAISERS BUILDING, 630 SANSOME ST. SAN FRANCISCO, CA.
Mar 20, 2025PA0004$0PA0004 TO TRANSFER CO DUTIES FOR DB SANSOME ROOF PROJECT AT U.S. APPRAISERS BUILDING, 630 SANSOME ST., SAN FRANCISCO, CA.
Jan 22, 2025PS0003$5.0KTHE PURPOSE OF THIS MODIFICATION IS TO AMEND THE SOW TO EXAMINE THE EXISTING MATERIALS LOCATED ON THE 16TH FLOOR MEZZANINE ROOF TO BETTER IDENTIFY DESIGN REQUIREMENTS. THE TOTAL CONTRACT AMOUNT IS BEING INCREASED TO $2,059,306.59.
Jan 15, 2025AA0002$0THE CONTRACTING OFFICER DUTIES FOR THIS TASK ORDER HAVE BEEN TRANSFERRED FROM DEBORAH TYSON TO LONNIE CUMMINGS
Nov 26, 2024PS0001$0MODIFICATION TO INCORPORATE THE BASE SCHEDULE AT TIME OF NOTICE TO PROCEED AND TO SYNC UP THE CONTRACT END DATE ON THE SANSOME ROOF PROJECT, SF, CA

Research next steps

  1. Verify whether remaining options may extend performance beyond the current end date.
  2. Confirm the ordering vehicle and your eligibility or a qualified teaming route.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.