Federal contract award

47PM0324C0004

GSA HAS A REQUIREMENT FOR A DESIGN-BUILD CONTRACT FOR THE REPLACEMENT OF THE FIRE PUMP SYSTEM AT 4600 SILVER HILL ROAD

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyGeneral Services Administration
OfficePBS R11 CONSTRUCTION SERVICES DIVSION CENTER 3
NAICS236220 — Commercial and Institutional Building Construction
PSCZ2AA — REPAIR OR ALTERATION OF OFFICE BUILDINGS
Parent award / vehicleNot reported
Set-aside8(A) SOLE SOURCE
Pricing typeFIRM FIXED PRICE
Obligations$413.0K
Current contract value$413.0K
Potential contract value / ceiling$413.0K
Start dateApr 10, 2024
Current end dateFeb 27, 2026
Potential end dateApr 27, 2026
Latest award activitySep 15, 2025
Source loadedAug 15, 2026

Funding and modification history

Showing the latest 4 of 4 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Sep 15, 2025PS0005$0EXTEND PERIOD OF PERFORMANCE 66 DAYS FROM NOVEMBER 18, 2025 TO FEBRARY 27, 2026 AT NO COST TO THE GOVERNMENT FOR CENSUS BUREAU FIRE PUMP REPLACEMENT AT 4600 SILVER HILL ROAD, SUTILAND MARYLAND 20746.
Jun 17, 2025PS0004$65.5KMODIFY CONTRACT TO REPLACE PIPING, CONCRETE PATCHING, FIRE PUMP/DESIGN EQUIPMENT AND EXTEND PERIOD OF PERFORMANCE 60 CALENDAR DAYS FOR FIRE PUMP REPLACEMENT 4600 SILVER HILL ROAD NORTH BUILDING LOCATED AT 4600 SILVER HILL RD, SUITLAND, MD 20746.
Apr 30, 2025PS0003$0IMPLEMENTATION OF CONTRACT DEVIATIONS AND CONTRACT CLAUSES VIA EXECUTIVE ORDER.
Apr 1, 2025PS0002$0MODIFY CONTRACT #47PM0324C0004, FIRE PUMP REPLACEMENT, CENSUS BUREAU NORTH BUILDING AT 4600 SILVER HILL ROAD, SUITLAND, MD FOR A 173 CALENDAR DAY NO COST TIME EXTENSION FROM APRIL 05, 2025 TO AUGUST 20, 2025.

Research next steps

  1. Verify whether remaining options may extend performance beyond the current end date.
  2. Check the stated set-aside against the solicitation and current certifications.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.