Federal contract award
47PM0421F0017
EO14042: TO ADD COVID CLAUSE
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | General Services Administration |
| Office | PBS R11 CONSTRUCTION SERVICES DIVSION CENTER 4 |
| NAICS | 541611 — Administrative Management and General Management Consulting Services |
| PSC | R499 — Other Professional Services |
| Parent award / vehicle | 47PD0319A0026 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $1.9M |
| Current contract value | $1.9M |
| Potential contract value / ceiling | $1.9M |
| Start date | Feb 8, 2021 |
| Current end date | Feb 28, 2026 |
| Potential end date | Mar 28, 2026 |
| Latest award activity | Feb 4, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 8 of 8 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Feb 4, 2026 | PS0017 | $53.3K | ADDITIONAL LABOR HOURS ADDED TO FINISH BY 2/28/2026 |
| Dec 3, 2025 | PS0016 | $79.9K | ADDITIONAL LABOR HOURS ADDED TO FINISH BY 12/31/2025 |
| Sep 23, 2025 | PS0015 | $0 | POP EXT END DATE FROM OCT TO NOV 2025 |
| Jul 16, 2025 | PS0014 | $78.1K | ADDITIONAL HOURS FOR FIRE ENGINEER |
| May 13, 2025 | PS0013 | $62.5K | ADDITIONAL HOURS FOR CM AND TECH FOR FIRE ALARM INSTALL |
| Mar 3, 2025 | PS0012 | $62.5K | ADDITIONAL CM SERVICES RONALD REAGAN BUILDING, 1300 PENNSYLVANIA AVE. N.W. WASHINGTON D.C |
| Jan 7, 2025 | PS0011 | $62.5K | ADDITIONAL CM SERVICES NEEDED FIRE ALARM PROJECT RONALD REAGAN BUILDING, 1300 PENNSYLVANIA AVE. N.W. WASHINGTON D.C |
| Nov 7, 2024 | PS0010 | $83.3K | CM SERVICES FIRE ALARM PROJECT RONALD REAGAN BUILDING, 1300 PENNSYLVANIA AVE. N.W. WASHINGTON D.C |
Research next steps
- Verify whether remaining options may extend performance beyond the current end date.
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.