Federal contract award
47PM0424C0028
CONDUCT ENGINEERING STUDY TO PROVIDE THE ENERGY SAVING MEANS NECESSARY AND THEN PERFORM THE WORK OF RETROFITTING LIGHTING IN THE COMMON AREAS THAT UTILIZE T8 BULBS IN THE DOUGLAS MUNRO BUILDING
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | General Services Administration |
| Office | PBS R11 CONSTRUCTION SERVICES DIVSION CENTER 4 |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Z2AA — REPAIR OR ALTERATION OF OFFICE BUILDINGS |
| Parent award / vehicle | Not reported |
| Set-aside | 8(A) SOLE SOURCE |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $806.0K |
| Current contract value | $806.0K |
| Potential contract value / ceiling | $806.0K |
| Start date | Sep 26, 2024 |
| Current end date | Jul 15, 2025 |
| Potential end date | Oct 15, 2025 |
| Latest award activity | May 7, 2025 |
| Source loaded | Aug 15, 2026 |
Funding and modification history
Showing the latest 3 of 3 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 7, 2025 | PC0002 | $332.4K | EXERCISE OPTION TO ADD ON THE ADDITIONAL FUNDS NECESSARY FOR THE REMAINING WORK OF THE REQUIREMENT. |
| Apr 8, 2025 | PS0003 | $0 | MOD FOR THE IMPLEMENTATION OF CDS AND DRONES CLAUSE |
| Oct 24, 2024 | AA0001 | $0 | ISSUE NTP AND ESTABLISH POP DATES |
Research next steps
- Verify whether remaining options may extend performance beyond the current end date.
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.