Federal contract award
47PM1123C0004
ARGON DISTRIBUTION SYSTEMS AT HARVEY W WILEY BUILDING
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | General Services Administration |
| Office | PBS R11 SPECIAL PROGRAMS FDA 80 BRANCH |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Z2AA — REPAIR OR ALTERATION OF OFFICE BUILDINGS |
| Parent award / vehicle | Not reported |
| Set-aside | 8(A) SOLE SOURCE |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $1.3M |
| Current contract value | $1.3M |
| Potential contract value / ceiling | $1.3M |
| Start date | Jun 8, 2023 |
| Current end date | Jan 15, 2026 |
| Potential end date | Feb 15, 2026 |
| Latest award activity | Oct 28, 2025 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 6 of 6 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Oct 28, 2025 | PS0010 | $0 | NO COST TIME EXTENSION OF PERIOD OF PERFORMANCE FROM 11/13/2025 THROUGH 1/15/2026. |
| May 14, 2025 | PA0009 | $0 | ADMIN MOD TO CHANGE COR FROM GAJIBOYE TO SHAYAN ABADIAN |
| Apr 24, 2025 | PA0008 | $0 | ADMINISTRATIVE MOD TO CHANGE COR |
| Apr 9, 2025 | PS0007 | $0 | IMPLEMENTATION OF CDS AND DRONES CLAUSE |
| Feb 18, 2025 | PS0006 | $22.2K | MODIFICATION TO INCORPORATE ADDITIONAL SCOPE OF WORK. |
| Jan 21, 2025 | PS0005 | $0 | NO COST TIME EXTENSION OF PERFORMANCE FROM 1/28/2025 TO 11/13/2025. |
Research next steps
- Verify whether remaining options may extend performance beyond the current end date.
- Check the stated set-aside against the solicitation and current certifications.