Federal contract award
47PM1123F0015
BUILDING H RENOVATION AT THE CENTER FOR VETERINARY MEDICINE IN LAUREL, MD
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | General Services Administration |
| Office | PBS R11 SPECIAL PROGRAMS FDA 80 BRANCH |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Z2AA — REPAIR OR ALTERATION OF OFFICE BUILDINGS |
| Parent award / vehicle | 47PM0518D0007 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $1.8M |
| Current contract value | $1.8M |
| Potential contract value / ceiling | $1.8M |
| Start date | Sep 27, 2023 |
| Current end date | Aug 31, 2026 |
| Potential end date | Sep 30, 2026 |
| Latest award activity | Aug 7, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 14 of 14 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Aug 7, 2026 | PS0013 | $0 | THIS IS A 30-DAY NO COST TIME EXTENSION FOR THE MATOC IDIQ - BUILDING H CONSTRUCTION PROJECT. |
| May 26, 2026 | PS0012 | $54.5K | THIS REQUIREMENT IS A COST AND TIME EXTENTION TO THE MATOC IDIQ - BUILDING H CONSTRUCTION PROJECT LOCATED AT H-AQUACULTURE, LAUREL, MD |
| May 1, 2026 | PS0011 | $0 | NO COST TIME EXTENSION TO EXTEND THE PERIOD OF PERFORMANCE 29 CALENDAR DAYS. |
| Feb 24, 2026 | PS0010 | $0 | BUILDING H CONSTRUCTION- NO COST TIME EXTENSION |
| Dec 9, 2025 | PS0009 | $8.8K | SUPPLEMENTAL MOD |
| Sep 17, 2025 | PS0008 | $74.9K | SUPPLEMENTAL WORK |
| Jun 18, 2025 | PS0007 | $-12.3K | 47PM1123F0015, MOD PS0007 - MATOC IDIQ - BUILDING H CONSTRUCTION- DEFINITIZE PART 2 OF PDL, LAUREL, MD |
| May 7, 2025 | PC0006 | $60.0K | CHANGE THE COR FROM: HARISH KAPUR TO: KULBIR SINGH. CONSTRUCTION SERVICES CHANGE ORDER TO INCLUDE ADDITIONAL WORK TO THE SOW FOR THE PROJECT, MATOC IDIQ- BUILDING H CONSTRUCTION, LAUREL, MD. |
| Apr 17, 2025 | PA0005 | $0 | ADMINISTRATIVE MOD TO CORRECT THE PERIOD OF PERFORMANCE END DATE TO JULY 23, 2025. |
| Apr 9, 2025 | PS0004 | $32.2K | MATOC IDIQ - BUILDING H CONSTRUCTION- REA |
| Dec 12, 2024 | PS0003 | $0 | MODIFICATION FOR NO COST TIME EXTENSION FOR THE BUILDING H RENOVATION FROM 12/13/2024 TO 04/24/2025 |
| Jul 16, 2024 | PA0002 | $0 | POP EXTENSION NO COST |
| Jun 4, 2024 | PS0001 | $59.6K | REQUIREMENT IS TO INCORPORATE THE REVISED STATEMENT OF WORK AND CONSTRUCTION MODIFICATION #001 DATE APRIL 16, 2024. THE CONTRACT COMPLETION DATE HAS BEEN EXTENDED BY 129 CALENDAR DAYS TO, DEC 13, 2024. |
| Sep 27, 2023 | 0 | $1.5M | BUILDING H RENOVATION AT THE CENTER FOR VETERINARY MEDICINE IN LAUREL, MD |
Research next steps
- Verify whether remaining options may extend performance beyond the current end date.
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.