Federal contract award
68HE0122F0044
SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START) 8-A CONTRACT BROWNFIELDS TASK ORDER
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Environmental Protection Agency |
| Office | REGION 1 CONTRACTING OFFICE |
| NAICS | 562910 — Remediation Services |
| PSC | B510 — Environmental Studies and Assessments |
| Parent award / vehicle | 68HE0122D0001 |
| Set-aside | Not reported |
| Pricing type | TIME AND MATERIALS |
| Obligations | $18.0M |
| Current contract value | $18.0M |
| Potential contract value / ceiling | $18.0M |
| Start date | Sep 16, 2022 |
| Current end date | Sep 15, 2027 |
| Potential end date | Sep 15, 2027 |
| Latest award activity | Sep 2, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 68 of 68 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Sep 9, 2026 | P00067 | $0 | START BROWNFIELDS TASK ORDER ADD SITES ALLOCATION APPROVAL PSC B510 |
| Sep 2, 2026 | P00066 | $0 | START BROWNFIELDS TASK ORDER ADD SITES ALLOCATION APPROVAL PSC B510 |
| Aug 12, 2026 | P00065 | $0 | START BROWNFIELDS TASK ORDER ADD SITES ALLOCATION APPROVAL PSC B510 |
| Aug 6, 2026 | P00064 | $0 | START BROWNFIELDS TASK ORDER ADD SITES ALLOCATION APPROVAL PSC B510 |
| Jul 27, 2026 | P00063 | $0 | START BROWNFIELDS TASK ORDER ADD SITES ALLOCATION APPROVAL PSC B510 |
| Jul 14, 2026 | P00062 | $0 | START BROWNFIELDS TASK ORDER ADD SITES ALLOCATION APPROVAL PSC B510 |
| Jun 24, 2026 | P00061 | $0 | START BROWNFIELDS TASK ORDER ADD SITES ALLOCATION APPROVAL PSC B510 |
| Jun 4, 2026 | P00060 | $0 | START BROWNFIELDS TASK ORDER ADD SITES ALLOCATION APPROVAL PSC B510 |
| May 11, 2026 | P00059 | $3.7M | START BROWNFIELDS TASK ORDER ADD SITES ALLOCATION APPROVAL AND IF PSC B510 |
| Apr 16, 2026 | P00058 | $0 | START BROWNFIELDS TASK ORDER ADD SITES ALLOCATION APPROVAL AND ADD CORS PSC B510 |
| Mar 25, 2026 | P00057 | $0 | START BROWNFIELDS TASK ORDER ADD SITES ALLOCATION APPROVAL PSC B510 |
| Jan 26, 2026 | P00056 | $0 | START BROWNFIELDS TASK ORDER ADD SITES ALLOCATION APPROVAL PSC B510 |
| Jan 8, 2026 | P00055 | $0 | START BROWNFIELDS TASK ORDER ADD SITES ALLOCATION APPROVAL PSC B510 |
| Oct 15, 2025 | P00054 | $0 | START BROWNFIELDS TASK ORDER ADD SITES ALLOCATION APPROVAL PSC B510 |
| Oct 9, 2025 | P00053 | $0 | START BROWNFIELDS TASK ORDER ADD SITES ALLOCATION APPROVAL PSC B510 |
| Sep 12, 2025 | P00052 | $0 | START BROWNFIELDS TASK ORDER ADD SITES ALLOCATION APPROVAL PSC B510 |
| Jul 11, 2025 | P00051 | $0 | START BROWNFIELDS TASK ORDER ADD SITES ALLOCATION APPROVAL PSC B510 |
| Jun 11, 2025 | P00050 | $0 | START BROWNFIELDS TASK ORDER ADD SITES ALLOCATION APPROVAL PSC B510 |
| May 16, 2025 | P00049 | $0 | START BROWNFIELDS TASK ORDER ADD SITES ALLOCATION APPROVAL |
| May 8, 2025 | P00048 | $0 | START BROWNFIELDS TASK ORDER ADD SITES ALLOCATION APPROVAL |
| Apr 16, 2025 | P00047 | $0 | START BROWNFIELDS TASK ORDER ADD SITES ALLOCATION APPROVAL |
| Mar 13, 2025 | P00046 | $0 | START BROWNFIELDS TASK ORDER ALLOCATION APPROVALS AND REVISED SOW |
| Feb 10, 2025 | P00045 | $0 | START BROWNFIELDS TASK ORDER ALLOCATION APPROVALS AND REVISED SOW |
| Jan 15, 2025 | P00043 | $4.8M | START BROWNFIELDS TASK ORDER ADD SITES: WENDELL ROAD AMD A AND 9 GREEN STREET AMD A ALLOCATION APPROVALS AND 2025 INCREMENTAL FUNDING |
| Jan 15, 2025 | P00044 | $0 | START BROWNFIELDS TASK ORDER ADMIN CHANGE |
| Dec 19, 2024 | P00041 | $0 | START BROWNFIELDS TASK ORDER ADD SITES ALLOCATION APPROVAL |
| Dec 19, 2024 | P00042 | $0 | START BROWNFIELDS TASK ORDER ADD SITES ALLOCATION APPROVAL |
| Nov 6, 2024 | P00040 | $0 | START BROWNFIELDS TASK ORDER ADD SITES ALLOCATION APPROVAL |
| Sep 26, 2024 | P00039 | $0 | START BROWNFIELDS TASK ORDER ADD SITES ALLOCATION APPROVAL |
| Jul 24, 2024 | P00038 | $0 | START BROWNFIELDS TASK ORDER ADD SITES ALLOCATION APPROVAL |
| Jul 11, 2024 | P00037 | $0 | START BROWNFIELDS TASK ORDER ADD SITES ALLOCATION APPROVAL |
| Jun 21, 2024 | P00036 | $0 | START BROWNFIELDS TASK ORDER ADD SITES ALLOCATION APPROVAL |
| May 30, 2024 | P00035 | $0 | START BROWNFIELDS TASK ORDER ADD SITES ALLOCATION APPROVAL |
| May 13, 2024 | P00034 | $0 | START BROWNFIELDS TASK ORDER ADD SITE: OLD GAS STATION TBA PROJECT # 68HE0122F0044-17 AMD C AND 41-43 ORANGE STREET TBA SITE PROJECT # 68HE0122F0044-10 AMD B , ALLOCATION APPROVAL |
| Apr 22, 2024 | P00033 | $0 | START BROWNFIELDS TASK ORDER ADD SITE: HOCKANUM TBA SITE PROJECT # 68HE0122F0044-30, FALMOUTH ST 68HE0122F0044-28, MEDWAY BLOCK AMD A, NOAH WEBSTER CLOSEOUT, NATHAN HALE CLOSEOUT ALLOCATION APPROVAL |
| Mar 28, 2024 | P00032 | $0 | START BROWNFIELDS TASK ORDER ADD SITE: SOMERS INDUSTRIAL FINISH TBA SITE PROJECT # 68HE0122F0044-27, LEON LITTLE & SONS FORMER L&M SERVICE STATION, FORMER L&M SERVICE STATION AMD C ALLOCATION APPROVAL |
| Mar 7, 2024 | P00031 | $0 | START BROWNFIELDS TASK ORDER ADD SITE: PORTLAND HARBOR WHARVES TBA SITE PROJECT # 68HE0122F0044-26, MEADOWOOD FIRE AMD A, OLD GAS STATION TBA AMD B, EAST END BRIDGEPORT SITES AMD A, LINCOLN PULP AND TISSUE MILL TBA AMD A ALLOCATION APPROVALS |
| Feb 13, 2024 | P00030 | $2.5M | START BROWNFIELDS TASK ORDER CLOSEOUT SITE: GREAT NORTHERN PAPER MILL TBA SITE AMENDMENT B PROJECT # 68HE0122F0044-2 CLOSEOUT APPROVAL AND FUNDING |
| Jan 19, 2024 | P00029 | $0 | START BROWNFIELDS TASK ORDER ADD SITE: FORMER L&M SERVICE STATION TBA SITE AMENDMENT B PROJECT # 68HE0122F0044-4 ALLOCATION APPROVAL |
| Dec 28, 2023 | P00028 | $0 | START BROWNFIELDS TASK ORDER AOC SITES: LUDLOW MILLS AMD B TBA SITE PROJECT # 68HE0122F0044-6, NOLUMBEKA PROJECT AMD B TBA 68HE0122F0044-1 ALLOCATION APPROVALS |
| Dec 11, 2023 | P00027 | $0 | START BROWNFIELDS TASK ORDER ADD SITE: RIED CLEANERS AMD A TBA SITE PROJECT # 68HE0122F0044-7, ORANGE STREET CHELSEA TBA 68HE0122F0044- 10 ALLOCATION APPROVALS |
| Dec 5, 2023 | P00026 | $0 | START BROWNFIELDS TASK ORDER ADD SITE: BALL AND SOCKET ARTS AMD B TBA SITE PROJECT # 68HE0122F0044-18, FORMER TOY FACTORY TBA 68HE0122F0044-24, 9 GREEN STREET TBA ALLOCATION APPROVALS |
| Oct 31, 2023 | P00025 | $0 | START BROWNFIELDS TASK ORDER ADD SITE: ST. JOHNSBURY ARMORY AMD B TBA SITE PROJECT # 68HE0122F0044-13 ALLOCATION APPROVALS |
| Oct 27, 2023 | P00024 | $0 | START BROWNFIELDS TASK ORDER ADD SITE: ST. JOHNSBURY ARMORY AMD A TBA SITE PROJECT # 68HE0122F0044-13 ALLOCATION APPROVALS |
| Oct 18, 2023 | P00023 | $0 | START BROWNFIELDS TASK ORDER ADD SITES: FORMER FARMINGTON FIRE STATION TBA SITE PROJECT # 68HE0122F0044-14 AMD A ALLOCATION APPROVALS |
| Oct 11, 2023 | P00022 | $0 | START BROWNFIELDS TASK ORDER ADD SITES: FORMER L&M SERVICE STATION TBA SITE AMD A AND MEADOWOOD FIRE STATION TBA SITE AMD A ALLOCATION APPROVALS |
| Sep 13, 2023 | P00021 | $30.7K | START BROWNFIELDS TASK ORDER ADD SITES: BALL AND SOCKET ARTS TBA AMD A ALLOCATION APPROVALS AND FUNDING |
| Aug 30, 2023 | P00020 | $0 | START BROWNFIELDS TASK ORDER ADD SITES: CONCORD STABLES TBA, LINCOLN PULP AND TISSUE MILL TBA, AMERICAN TISSUE MILL AMD C ALLOCATION APPROVALS |
| Aug 2, 2023 | P00019 | $0 | START BROWNFIELDS TASK ORDER ADD SITES: NOLUMBEKA AMD A, NATHAN HALE SCHOOL AMD A, 355 WENDELL ROAD, AMERICAN TISSUE MILL AMD B, NOAH WEBSTER SCHOOL AMD A ALLOCATION APPROVALS |
| Jul 17, 2023 | P00018 | $500.1K | START BROWNFIELDS TASK ORDER ADD SITES: BALL AND SOCKET ARTS, PORTLAND HARBOR AMD A, MEDWAY BLOCK, OLD GAS STATION AMD A ALLOCATION APPROVALS AND INCREMENTAL FUNDING |
| Jun 13, 2023 | P00017 | $0 | START BROWNFIELDS TASK ORDER ADD SITE: ST. JOHNSBURY ARMORY 68HE0122F0044-13 ALLOCATION APPROVAL |
| May 26, 2023 | P00016 | $0 | START BROWNFIELDS TASK ORDER ADD SITE: FORMER FARMINGTON 68HE0122F0044-14, NOAH WEBSTER 68HE0122F0044-16, OLD GAS STATION 68HE0122F0044-17, MEADOWOOD FIRE TBA 68HE0122F0044-19 ALLOCATION APPROVAL |
| May 1, 2023 | P00015 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START) 8-A CONTRACT BROWNFIELDS TASK ORDER ADD SITE: GREAT NORTHER PAPER MILL AMD A 68HE0122F0044-2 TBA ALLOCATION APPROVAL |
| Apr 18, 2023 | P00014 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START) 8-A CONTRACT BROWNFIELDS TASK ORDER ADD SITE: 55 WESTON AVE 68HE0122F0044-12 TBA ALLOCATION APPROVAL |
| Apr 5, 2023 | P00013 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START) 8-A CONTRACT BROWNFIELDS TASK ORDER ADD SITE: ORANGE STREET CHELSEA TBA AND NATHAN HALE SCHOOL TBA ALLOCATION APPROVAL |
| Apr 4, 2023 | P00012 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START) 8-A CONTRACT BROWNFIELDS TASK ORDER ADD SITE: LUDLOW MILLS AMD A ALLOCATION APPROVAL |
| Mar 20, 2023 | P00011 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START) 8-A CONTRACT BROWNFIELDS TASK ORDER ADD SITE: EAST END BRIDGEPORT SITES 68HE0122F0044-9 ALLOCATION APPROVAL |
| Mar 9, 2023 | P00010 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START) 8-A CONTRACT BROWNFIELDS TASK ORDER ADD SITE: PORTLAND HARBOR TBA SITE 68HE0122F0044-8 ALLOCATION APPROVAL |
| Mar 1, 2023 | P00009 | $2.5M | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START) 8-A CONTRACT BROWNFIELDS TASK ORDER INCREMENTAL FUNDING BROWNFIELDS |
| Feb 27, 2023 | P00008 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START) 8-A CONTRACT BROWNFIELDS TASK ORDER ADD SITE: AMERICAN TISSUE MILL AMD A ALLOCATION APPROVAL |
| Feb 6, 2023 | P00007 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START) 8-A CONTRACT BROWNFIELDS TASK ORDER ADD SITE: LUDLOW MILLS SITE ALLOCATION APPROVAL |
| Jan 30, 2023 | P00006 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START) 8-A CONTRACT BROWNFIELDS TASK ORDER ADD SITE: RIED CLEANERS SITE ALLOCATION APPROVAL |
| Jan 24, 2023 | P00005 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START) 8-A CONTRACT BROWNFIELDS TASK ORDER ADD SITE: FORMER L&M SERVICE STATION-TBA SITE ALLOCATION APPROVAL |
| Jan 11, 2023 | P00004 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START) 8-A CONTRACT BROWNFIELDS TASK ORDER ADD SITE: BALLOUVILLE MILL -TBA APPROVAL AND COR CHANGE |
| Nov 21, 2022 | P00003 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START) 8-A CONTRACT BROWNFIELDS TASK ORDER ADD SITE: NOLUMBEKA PROJECT TBA SITE ALLOCATION APPROVAL |
| Nov 15, 2022 | P00002 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START) 8-A CONTRACT BROWNFIELDS TASK ORDER ADD SITE: AMERICAN TISSUE MILL ALLOCATION APPROVAL |
| Nov 14, 2022 | P00001 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START) 8-A CONTRACT BROWNFIELDS TASK ORDER ADD SITE: GREAT NORTHERN PAPER ALLOCATION APPROVAL |
| Sep 16, 2022 | 0 | $4.0M | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START) 8-A CONTRACT BROWNFIELDS TASK ORDER |
Estimated positioning window
Oct 25, 2026 – Mar 15, 2027
75/100
Why this recompete signal
Contract timing and recorded acquisition signals at the time of calculation.
Stored score: 75/100. Available recorded signals: 70 points.
- Contract end 2027-09-15 (325 days from calculation)
- +35 points
- 4 historical awards in this buyer and category group
- +15 points
- 68 recorded award transactions
- +10 points
- Latest award action: 2026-09-02
- +5 points
- Parent award identifier recorded
- +5 points
- Solicitation identifier recorded
- +0 points
- Linked official forecast
- +0 points
- Calculated on
- 2026-10-25 10:18:04.631876+00:00
The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.
Rule-based research score; it does not measure your chance of winning.
This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.
Recompete score calculated Oct 25, 2026.
Research next steps
- Check the linked forecast or SAM for a confirmed solicitation and current timing.
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.