| Field | Reported value |
|---|---|
| Agency | Environmental Protection Agency |
| Office | REGION 5 CONTRACTING OFFICE |
| NAICS | 541620 — Environmental Consulting Services |
| PSC | R429 — SUPPORT- PROFESSIONAL: EMERGENCY RESPONSE/DISASTER PLANNING/PREPAREDNESS SUPPORT |
| Parent award / vehicle | 68HE0519D0005 |
| Set-aside | Not reported |
| Pricing type | TIME AND MATERIALS |
| Obligations | $57.4M |
| Current contract value | $57.4M |
| Potential contract value / ceiling | $57.4M |
| Start date | Jan 24, 2020 |
| Current end date | Apr 7, 2025 |
| Potential end date | Jul 31, 2025 |
| Latest award activity | Oct 7, 2025 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 154 of 154 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Oct 7, 2025 | P00153 | $-660.9K | DEOBLIGATE REMAINING EXCESS FUNDS IN THE AMOUNT OF $660,910.48 CLOSE TASK ORDER. |
| Jul 15, 2025 | P00152 | $-1.2M | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5. THE PURPOSE OF THIS MODIFICATION IS TO ADMINISTER TDTOLINS AND TO DEOBLIGATE FUNDING IN THE AMOUNT OF $1,205,000.00 FROM THIS TASK ORDER. |
| Apr 16, 2025 | P00151 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5. THE PURPOSE OF THIS MODIFICATION IS TO ADMINISTER ONE TDTOLIN TO THIS TASK ORDER. |
| Apr 7, 2025 | P00149 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5. THE PURPOSE OF THIS MODIFICATION IS TO ADMINISTER TDTOLINS TO THIS TASK ORDER. |
| Apr 7, 2025 | P00150 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5. THE PURPOSE OF THIS MODIFICATION IS TO ADMINISTER TDTOLINS TO THIS TASK ORDER. |
| Mar 24, 2025 | P00148 | $-245.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5. THE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE FUNDS IN THE AMOUNT OF $245,000.00. |
| Mar 19, 2025 | P00147 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, THE PURPOSE OF THIS MODIFICATION IS TO ADMINISTER TDTOLINS TO THIS TASK ORDER. |
| Mar 6, 2025 | P00146 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, THE PURPOSE OF THIS MODIFICATION IS TO ADMINISTER TDTOLINS TO THIS TASK ORDER. |
| Mar 5, 2025 | P00145 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, THE PURPOSE OF THIS MODIFICATION IS TO ADMINISTER TDTOLINS TO THIS TASK ORDER. |
| Mar 4, 2025 | P00144 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, THE PURPOSE OF THIS MODIFICATION IS TO ADMINISTER TDTOLINS TO THIS TASK ORDER. |
| Feb 27, 2025 | P00143 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, THE PURPOSE OF THIS MODIFICATION IS TO ADMINISTER TDTOLINS TO THIS TASK ORDER. |
| Feb 19, 2025 | P00142 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, THE PURPOSE OF THIS MODIFICATION IS TO ADMINISTER TDTOLINS TO THIS TASK ORDER. |
| Feb 10, 2025 | P00141 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, THE PURPOSE OF THIS MODIFICATION IS TO ADMINISTER TDTOLINS. |
| Feb 5, 2025 | P00140 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, THE PURPOSE OF THIS MODIFICATION IS TO ADMINISTER TDTOLINS. |
| Jan 30, 2025 | P00139 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, THE PURPOSE OF THIS MODIFICATION IS TO ADMINISTER TDTOLINS. |
| Jan 22, 2025 | P00138 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, THE PURPOSE OF THIS MODIFICATION IS TO ADMINISTER TDTOLINS. |
| Jan 17, 2025 | P00137 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, THE PURPOSE OF THIS MODIFICATION IS TO ADMINISTER TDTOLINS. |
| Jan 2, 2025 | P00136 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THIS TASK ORDER FROM 1/7/2025 TO 4/7/2025 AND ADMINISTRATIVE MODIFICATION TO ADMINISTER TDTOLINS. |
| Dec 19, 2024 | P00135 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, ADMINISTRATIVE MODIFICATION TO ADMINISTER TDTOLINS. |
| Dec 11, 2024 | P00134 | $245.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, OBLIGATE FUNDS IN THE AMOUNT OF $245,000.00 AND DEALLOCATE FUNDS FOR ADMINISTERING TDTOLINS. |
| Nov 27, 2024 | P00133 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, ADMINISTRATIVE MODIFICATION TO ADMINISTER TDTOLINS. |
| Nov 20, 2024 | P00132 | $29.5K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, OBLIGATE FUNDS IN THE AMOUNT OF $29,452.00, DEALLOCATION OF FUNDS FOR ADMINISTERING TDTOLINS, AND CLOSEOUT SIX TOLINS. |
| Oct 11, 2024 | P00131 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, ADMINISTRATIVE MODIFICATION FOR ADMINISTERING TDTOLINS. |
| Sep 26, 2024 | P00129 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, ADMINISTRATIVE MODIFICATION FOR ADMINISTERING THE TDTOLINS. |
| Sep 26, 2024 | P00130 | $150.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, OBLIGATE FUNDS IN THE AMOUNT OF $150,000.00. |
| Sep 16, 2024 | P00128 | $300.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, OBLIGATE FUNDS IN THE AMOUNT OF $300,000.00 IN BULK FUNDS. |
| Aug 29, 2024 | P00127 | $500.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, OBLIGATE FUNDS IN THE AMOUNT OF $500,000.00 IN BULK FUNDS. |
| Aug 27, 2024 | P00126 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, THIS ADMINISTRATIVE MOD IS TO CHANGE THE COR AND OSC, AND A DEALLOCATION ACTION. |
| Aug 19, 2024 | P00125 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, ADMINISTRATIVE MODIFICATION FOR ADMINISTERING THE TDTOLINS. |
| Aug 13, 2024 | P00124 | $7.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, OBLIGATE FUNDS IN THE AMOUNT OF $7,000.00. |
| Aug 12, 2024 | P00123 | $1.0M | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, OBLIGATE FUNDS IN THE AMOUNT OF $1,000,000.00. |
| Aug 6, 2024 | P00122 | $245.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, OBLIGATE FUNDS IN THE AMOUNT OF $245,000.00. |
| Jul 2, 2024 | P00121 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, CORRECTS THE DEALLOCATED AMOUNT AND TO THE ER BULK FUNDS. |
| Jun 12, 2024 | P00120 | $500.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, OBLIGATE FUNDS IN THE AMOUNT OF $500,000.00 IN BULK FUNDS. |
| Jun 5, 2024 | P00119 | $500.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, OBLIGATE FUNDS IN THE AMOUNT OF $500,000.00 FOR THE SUPPORT AT EAST PALESTINE TRAIN DERAILMENT. |
| May 16, 2024 | P00118 | $6.0M | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, OBLIGATE FUNDS IN THE AMOUNT OF $6,000,000.00 FOR THE SUPPORT AT EAST PALESTINE TRAIN DERAILMENT. |
| Apr 24, 2024 | P00117 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, BULK REMOVAL ACTIVITIES TASK ORDER FOR ADMINISTRATIVE MODIFICATION. |
| Apr 2, 2024 | P00116 | $500.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES, OBLIGATE FUNDS IN THE AMOUNT OF $500,000.00. |
| Mar 7, 2024 | P00115 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES, ADMINISTRATIVE MODIFICATION FOR ADMINISTERING THE TDTOLINS AND TO EXTEND THE POP. |
| Feb 13, 2024 | P00114 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES, ADMINISTRATIVE MODIFICATION WITH TDTOLINS |
| Jan 17, 2024 | P00113 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES, ADMINISTRATIVE MODIFICATION WITH TDTOLINS |
| Dec 6, 2023 | P00112 | $1.0M | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES, FUNDING PR TDTOLINS MOD |
| Nov 9, 2023 | P00111 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES, ADMINISTRATIVE TDTOLINS MOD |
| Oct 11, 2023 | P00110 | $6.0M | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES, FUNDING AND TDTOLINS MOD |
| Sep 13, 2023 | P00109 | $3.0M | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES, FUNDING AND TDTOLINS MOD |
| Sep 11, 2023 | P00108 | $650.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES, FUNDING AND TDTOLINS MOD |
| Aug 23, 2023 | P00107 | $250.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES, FUNDING AND TDTOLINS MOD |
| Aug 2, 2023 | P00106 | $335.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES, FUNDING AND TDTOLINS MOD |
| Jul 24, 2023 | P00105 | $6.0M | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES, FUNDING AND TDTOLINS MOD |
| Jul 12, 2023 | P00104 | $3.5M | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES, FUNDING AND TDTOLINS MOD |
| Jun 26, 2023 | P00103 | $2.4M | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES, FUNDING AND TDTOLINS MOD |
| Jun 1, 2023 | P00102 | $2.1M | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES, FUNDING MOD AND ADMIN ACTION TO CORRECT 0001CC101-002 MCPEEK LODGE PARK |
| Apr 27, 2023 | P00101 | $800.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES, FUNDING MODIFICATION |
| Apr 21, 2023 | P00100 | $3.0M | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES, FUNDING MODIFICATION |
| Apr 11, 2023 | P00099 | $50.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Apr 4, 2023 | P00098 | $2.0M | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Mar 29, 2023 | P00097 | $1.0M | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Mar 23, 2023 | P00096 | $1.1M | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Mar 15, 2023 | P00095 | $1.0M | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Mar 3, 2023 | P00094 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Feb 24, 2023 | P00093 | $1.0M | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Feb 17, 2023 | P00092 | $500.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Feb 13, 2023 | P00091 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Feb 7, 2023 | P00090 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Jan 24, 2023 | P00089 | $1.0M | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Jan 17, 2023 | P00088 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Dec 30, 2022 | P00087 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Dec 28, 2022 | P00086 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Dec 21, 2022 | P00085 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Dec 14, 2022 | P00084 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Dec 8, 2022 | P00083 | $-53.9K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Nov 22, 2022 | P00082 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Nov 3, 2022 | P00081 | $575.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Oct 13, 2022 | P00080 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Sep 30, 2022 | P00079 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Sep 27, 2022 | P00078 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Sep 19, 2022 | P00077 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Sep 6, 2022 | P00076 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Aug 16, 2022 | P00075 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Aug 9, 2022 | P00074 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Jul 26, 2022 | P00073 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Jul 20, 2022 | P00072 | $840.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Jul 1, 2022 | P00071 | $50.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Jun 24, 2022 | P00070 | $40.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Jun 21, 2022 | P00069 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Jun 1, 2022 | P00068 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| May 13, 2022 | P00067 | $500.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| May 10, 2022 | P00066 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| May 5, 2022 | P00065 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Apr 25, 2022 | P00064 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Apr 14, 2022 | P00063 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Apr 7, 2022 | P00062 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Mar 31, 2022 | P00061 | $1.0M | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Mar 30, 2022 | P00060 | $65.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Mar 14, 2022 | P00059 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Mar 11, 2022 | P00058 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Feb 14, 2022 | P00057 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Feb 10, 2022 | P00056 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Feb 8, 2022 | P00055 | $44.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Jan 26, 2022 | P00054 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Jan 19, 2022 | P00053 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Jan 4, 2022 | P00052 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Dec 15, 2021 | P00051 | $30.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Dec 8, 2021 | P00050 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Nov 17, 2021 | P00049 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Nov 2, 2021 | P00048 | $90.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Oct 15, 2021 | P00047 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Sep 29, 2021 | P00046 | $606.1K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Sep 23, 2021 | P00045 | $250.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Sep 21, 2021 | P00044 | $500.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Aug 17, 2021 | P00043 | $2.0M | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Jul 23, 2021 | P00042 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Jul 9, 2021 | P00041 | $30.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Jul 7, 2021 | P00040 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Jun 23, 2021 | P00039 | $1.2M | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Jun 8, 2021 | P00038 | $70.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| May 19, 2021 | P00037 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Apr 23, 2021 | P00036 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Mar 31, 2021 | P00035 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Mar 17, 2021 | P00034 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Mar 12, 2021 | P00033 | $200.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Mar 11, 2021 | P00032 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Mar 3, 2021 | P00031 | $125.0K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Feb 19, 2021 | P00030 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Feb 8, 2021 | P00029 | $1.0M | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Jan 20, 2021 | P00028 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Dec 21, 2020 | P00027 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Nov 27, 2020 | P00026 | $0 | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Nov 6, 2020 | P00025 | $0 | SUPERFUND TECHNICAL ASSESSMENT&RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Oct 16, 2020 | P00024 | $0 | SUPERFUND TECHNICAL ASSESSMENT&RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Sep 22, 2020 | P00023 | $450.0K | SUPERFUND TECHNICAL ASSESSMENT&RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Sep 3, 2020 | P00022 | $0 | SUPERFUND TECHNICAL ASSESSMENT&RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Aug 7, 2020 | P00021 | $0 | SUPERFUND TECHNICAL ASSESSMENT&RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Jul 9, 2020 | P00020 | $0 | SUPERFUND TECHNICAL ASSESSMENT&RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Jun 26, 2020 | P00019 | $1.5M | SUPERFUND TECHNICAL ASSESSMENT&RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Jun 16, 2020 | P00018 | $231.6K | SUPERFUND TECHNICAL ASSESSMENT&RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Jun 8, 2020 | P00017 | $0 | SUPERFUND TECHNICAL ASSESSMENT&RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Jun 1, 2020 | P00016 | $0 | SUPERFUND TECHNICAL ASSESSMENT&RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| May 14, 2020 | P00015 | $0 | SUPERFUND TECHNICAL ASSESSMENT&RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| May 5, 2020 | P00014 | $0 | SUPERFUND TECHNICAL ASSESSMENT&RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Apr 30, 2020 | P00013 | $0 | SUPERFUND TECHNICAL ASSESSMENT&RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Apr 20, 2020 | P00012 | $331.5K | SUPERFUND TECHNICAL ASSESSMENT&RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Apr 13, 2020 | P00011 | $0 | SUPERFUND TECHNICAL ASSESSMENT&RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Apr 6, 2020 | P00010 | $0 | SUPERFUND TECHNICAL ASSESSMENT&RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Mar 30, 2020 | P00009 | $0 | SUPERFUND TECHNICAL ASSESSMENT&RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Mar 27, 2020 | P00008 | $-486.3K | SUPERFUND TECHNICAL ASSESSMENT&RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Mar 24, 2020 | P00007 | $900.0K | SUPERFUND TECHNICAL ASSESSMENT&RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Mar 18, 2020 | P00006 | $0 | SUPERFUND TECHNICAL ASSESSMENT&RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Mar 11, 2020 | P00005 | $0 | SUPERFUND TECHNICAL ASSESSMENT&RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Feb 28, 2020 | P00004 | $0 | SUPERFUND TECHNICAL ASSESSMENT&RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Feb 11, 2020 | P00003 | $70.5K | SUPERFUND TECHNICAL ASSESSMENT&RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Feb 10, 2020 | P00002 | $0 | SUPERFUND TECHNICAL ASSESSMENT&RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Feb 6, 2020 | P00001 | $390.0K | SUPERFUND TECHNICAL ASSESSMENT&RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
| Jan 24, 2020 | 0 | $250.0K | SUPERFUND TECHNICAL ASSESSMENT&RESPONSE TEAM (START), REGION 5, TASK ORDER FOR BULK REMOVAL ACTIVITIES |
Research next steps
- Verify whether remaining options may extend performance beyond the current end date.
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.