Federal contract award
68HE0722F0043
SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM 5 (START V) CONTRACT FOR EPA REGION 7 - SITE/PROJECT NAME: NEBRASKA SITE ASSESSMENTS.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Environmental Protection Agency |
| Office | REGION 7 CONTRACTING OFFICE |
| NAICS | 541620 — Environmental Consulting Services |
| PSC | R429 — SUPPORT- PROFESSIONAL: EMERGENCY RESPONSE/DISASTER PLANNING/PREPAREDNESS SUPPORT |
| Parent award / vehicle | 68HE0719D0001 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $476.3K |
| Current contract value | $476.3K |
| Potential contract value / ceiling | $476.3K |
| Start date | Feb 11, 2022 |
| Current end date | Aug 25, 2025 |
| Potential end date | Dec 17, 2025 |
| Latest award activity | Dec 16, 2025 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 11 of 11 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Dec 16, 2025 | P00010 | $-89.7K | R7 START V: NEBRASKA SITE ASSESSMENTS TECHNICAL SUPPORT MOD P00010: DEOBLIGATE $89,683.02 AND CLOSE OUT TASK ORDER |
| Apr 14, 2025 | P00009 | $0 | R7 START V: NEBRASKA SITE ASSESSMENTS TECHNICAL SUPPORT MOD P00009: NEBRASKA SITE ASSESSMENT SUB-TASK 007 FOR DRY CLEANER PAS |
| Apr 4, 2025 | P00008 | $158.4K | R7 START V: NEBRASKA SITE ASSESSMENTS TECHNICAL SUPPORT MOD P00008: ADDITIONAL LEVEL OF EFFORT FOR REMOVAL ASSESSMENT. |
| Mar 27, 2025 | P00007 | $0 | R7 START V: NEBRASKA SITE ASSESSMENTS TECHNICAL SUPPORT MOD P00007: CHANGE TO STATEMENT OF WORK FOR THE BASE TASK ORDER |
| Mar 6, 2025 | P00006 | $0 | R7 START V: NEBRASKA SITE ASSESSMENTS TECHNICAL SUPPORT MOD P00006: SUBTASK 006 FOR RUTHS NORGE ISAS NEBRASKA SITE ASSESSMENT |
| Feb 28, 2024 | P00005 | $162.4K | R7 START V: NEBRASKA SITE ASSESSMENTS TECHNICAL SUPPORT MOD P00005: ADDITIONAL LEVEL OF EFFORT FOR REMOVAL ASSESSMENT. |
| Dec 19, 2023 | P00003 | $0 | R7 START V: NEBRASKA SITE ASSESSMENTS TECHNICAL SUPPORT MOD P00003: ISSUE SUBTASK 004 FOR PRE-CERCLA PRELIMINARY ASSESSMENT |
| Dec 19, 2023 | P00004 | $0 | R7 START V: NEBRASKA SITE ASSESSMENTS TECHNICAL SUPPORT MOD P00004: ISSUE SUBTASK 005 TO COMPLETE PSS ASSESSMENTS IN NEBRASKA |
| Aug 4, 2023 | P00002 | $30.0K | R7 START V: NEBRASKA SITE ASSESSMENTS TECHNICAL SUPPORT MOD P00002: ISSUE SUBTASK 003 FOR FORMER ONE-HOUR MARTINIZING PRELIMINARY ASSESSMENT |
| Nov 15, 2022 | P00001 | $0 | R7 START V: NEBRASKA SITE ASSESSMENTS TECHNICAL SUPPORT MOD P00001: ISSUE SUBTASK 002 FOR PCS ASSESSMENTS |
| Feb 11, 2022 | 0 | $215.2K | SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM 5 (START V) CONTRACT FOR EPA REGION 7 - SITE/PROJECT NAME: NEBRASKA SITE ASSESSMENTS. |
Research next steps
- Verify whether remaining options may extend performance beyond the current end date.
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.