Federal contract award
69056723C000016
OR DOT 18(1), OR58: COAST FORK WILLAMETTE RIVER TO LOWER SALT CR BRIDGES. THE PRIMARY OBJECTIVE OF THE THIS PROJECT IS TO SEISMICALLY RETROFIT 3 BRIDGES ON OR-58 BETWEEN US-97 AND I-5. THE SCOPE OF WORK CONSISTS OF: STRUCTURE REPAIR, STRUCTURE SEISMI
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Transportation |
| Office | 690567 WESTERN FEDERAL LANDS DIV |
| NAICS | 237310 — Highway, Street, and Bridge Construction |
| PSC | Y1LB — CONSTRUCTION OF HIGHWAYS, ROADS, STREETS, BRIDGES, AND RAILWAYS |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $19.9M |
| Current contract value | $19.9M |
| Potential contract value / ceiling | $19.9M |
| Start date | Apr 17, 2023 |
| Current end date | Dec 5, 2025 |
| Potential end date | Jul 21, 2026 |
| Latest award activity | Jul 20, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 27 of 27 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jul 20, 2026 | P00026 | $0 | OR DOT 18(1), OR58: COAST FORK WILLAMETTE RIVER TO LOWER SALT CR BRIDGES. ADMINISTRATIVE MODIFICATION. |
| Mar 27, 2026 | P00025 | $0 | OR DOT 18(1), OR58: COAST FORK WILLAMETTE RIVER TO LOWER SALT CR BRIDGES. ADMINISTRATIVE MODIFICATION. |
| Dec 18, 2025 | P00024 | $0 | OR DOT 18(1), OR58: COAST FORK WILLAMETTE RIVER TO LOWER SALT CR BRIDGES. ADMINISTRATIVE MODIFICATION. |
| Oct 27, 2025 | P00023 | $0 | AWARD OPTION Z FOR PROJECT, OR DOT 18(1), OR58: COAST FORK WILLAMETTE RIVER TO LOWER SALT CR BRIDGES. |
| Sep 2, 2025 | P00022 | $631.0K | AWARD OPTION Z FOR PROJECT, OR DOT 18(1), OR58: COAST FORK WILLAMETTE RIVER TO LOWER SALT CR BRIDGES. |
| Aug 29, 2025 | P00020 | $140.0K | AWARD OPTION Z FOR PROJECT, OR DOT 18(1), OR58: COAST FORK WILLAMETTE RIVER TO LOWER SALT CR BRIDGES. |
| Aug 29, 2025 | P00021 | $169.2K | AWARD OPTION Z FOR PROJECT, OR DOT 18(1), OR58: COAST FORK WILLAMETTE RIVER TO LOWER SALT CR BRIDGES. |
| Aug 18, 2025 | P00019 | $3.5K | AWARD OPTION Z FOR PROJECT, OR DOT 18(1), OR58: COAST FORK WILLAMETTE RIVER TO LOWER SALT CR BRIDGES. |
| Jul 2, 2025 | P00018 | $0 | AWARD OPTION Z FOR PROJECT, OR DOT 18(1), OR58: COAST FORK WILLAMETTE RIVER TO LOWER SALT CR BRIDGES. |
| Apr 2, 2025 | P00017 | $0 | AWARD OPTION Z FOR PROJECT, OR DOT 18(1), OR58: COAST FORK WILLAMETTE RIVER TO LOWER SALT CR BRIDGES. |
| Mar 25, 2025 | P00016 | $0 | AWARD OPTION Z FOR PROJECT, OR DOT 18(1), OR58: COAST FORK WILLAMETTE RIVER TO LOWER SALT CR BRIDGES. |
| Mar 13, 2025 | P00015 | $0 | AWARD OPTION Z FOR PROJECT, OR DOT 18(1), OR58: COAST FORK WILLAMETTE RIVER TO LOWER SALT CR BRIDGES. |
| Feb 25, 2025 | P00014 | $0 | AWARD OPTION Z FOR PROJECT, OR DOT 18(1), OR58: COAST FORK WILLAMETTE RIVER TO LOWER SALT CR BRIDGES. |
| Nov 20, 2024 | P00013 | $0 | AWARD OPTION Z FOR PROJECT, OR DOT 18(1), OR58: COAST FORK WILLAMETTE RIVER TO LOWER SALT CR BRIDGES. |
| Nov 18, 2024 | P00012 | $0 | AWARD OPTION Z FOR PROJECT, OR DOT 18(1), OR58: COAST FORK WILLAMETTE RIVER TO LOWER SALT CR BRIDGES. |
| Sep 20, 2024 | P00011 | $0 | AWARD OPTION Z FOR PROJECT, OR DOT 18(1), OR58: COAST FORK WILLAMETTE RIVER TO LOWER SALT CR BRIDGES. |
| Sep 12, 2024 | P00010 | $588.0K | AWARD OPTION Z FOR PROJECT, OR DOT 18(1), OR58: COAST FORK WILLAMETTE RIVER TO LOWER SALT CR BRIDGES. |
| Jul 11, 2024 | P00009 | $11.9K | AWARD OPTION Z FOR PROJECT, OR DOT 18(1), OR58: COAST FORK WILLAMETTE RIVER TO LOWER SALT CR BRIDGES. |
| Jun 3, 2024 | P00008 | $0 | AWARD OPTION Z FOR PROJECT, OR DOT 18(1), OR58: COAST FORK WILLAMETTE RIVER TO LOWER SALT CR BRIDGES. |
| Apr 8, 2024 | P00007 | $-2.0K | AWARD OPTION Z FOR PROJECT, OR DOT 18(1), OR58: COAST FORK WILLAMETTE RIVER TO LOWER SALT CR BRIDGES. |
| Mar 29, 2024 | P00005 | $99.7K | AWARD OPTION Z FOR PROJECT, OR DOT 18(1), OR58: COAST FORK WILLAMETTE RIVER TO LOWER SALT CR BRIDGES. |
| Feb 21, 2024 | P00006 | $0 | AWARD OPTION Z FOR PROJECT, OR DOT 18(1), OR58: COAST FORK WILLAMETTE RIVER TO LOWER SALT CR BRIDGES. |
| Jan 17, 2024 | P00003 | $0 | AWARD OPTION Z FOR PROJECT, OR DOT 18(1), OR58: COAST FORK WILLAMETTE RIVER TO LOWER SALT CR BRIDGES. |
| Jan 17, 2024 | P00004 | $36.2K | AWARD OPTION Z FOR PROJECT, OR DOT 18(1), OR58: COAST FORK WILLAMETTE RIVER TO LOWER SALT CR BRIDGES. |
| Sep 19, 2023 | P00002 | $18.5K | AWARD OPTION Z FOR PROJECT, OR DOT 18(1), OR58: COAST FORK WILLAMETTE RIVER TO LOWER SALT CR BRIDGES. |
| May 24, 2023 | P00001 | $6.5M | AWARD OPTION Z FOR PROJECT, OR DOT 18(1), OR58: COAST FORK WILLAMETTE RIVER TO LOWER SALT CR BRIDGES. |
| Apr 17, 2023 | 0 | $11.7M | OR DOT 18(1), OR58: COAST FORK WILLAMETTE RIVER TO LOWER SALT CR BRIDGES. THE PRIMARY OBJECTIVE OF THE THIS PROJECT IS TO SEISMICALLY RETROFIT 3 BRIDGES ON OR-58 BETWEEN US-97 AND I-5. THE SCOPE OF WORK CONSISTS OF: STRUCTURE REPAIR, STRUCTURE SEISMI |
Buyer contacts from matching notices
Matched on exact award/solicitation identifier and awarding agency. Source dates describe the notice, not current contact verification.
| Contact | Role | Published contact methods | Evidence | Source date |
|---|---|---|---|---|
| Contracts G. Office | Contact | WFL.Contracts@dot.gov 3606197520 | Source | Nov 29, 2023 |
| Contracts G. Office | Contact | WFL.Contracts@dot.gov 3606197520 | Source | Mar 22, 2023 |
| Contracts G. Office | Contact | WFL.Contracts@dot.gov 3606197520 | Source | Mar 21, 2023 |
| Contracts G. Office | Contact | WFL.Contracts@dot.gov 3606197520 | Source | Mar 21, 2023 |
| Contracts G. Office | Contact | WFL.Contracts@dot.gov 3606197520 | Source | Mar 20, 2023 |
| Contracts G. Office | Contact | WFL.Contracts@dot.gov 3606197520 | Source | Mar 16, 2023 |
| Contracts G. Office | Contact | WFL.Contracts@dot.gov 3606197520 | Source | Mar 13, 2023 |
| Contracts G. Office | Contact | WFL.Contracts@dot.gov 3606197520 | Source | Mar 8, 2023 |
| Contracts G. Office | Contact | WFL.Contracts@dot.gov 3606197520 | Source | Mar 1, 2023 |
| Contracts G. Office | Contact | WFL.Contracts@dot.gov 3606197520 | Source | Feb 17, 2023 |
| Contracts G. Office | Contact | WFL.Contracts@dot.gov 3606197520 | Source | Jan 27, 2023 |
Research next steps
- Verify whether remaining options may extend performance beyond the current end date.
- Check the stated set-aside against the solicitation and current certifications.