Federal contract award
69056724F00003N
OR FLAP UMATILL 582(1), MILL CREEK ROAD ENGINEERING SUPPORT DURING ADVERTISEMENT AND CONSTRUCTION
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Transportation |
| Office | 690567 WESTERN FEDERAL LANDS DIV |
| NAICS | 541330 — Engineering Services |
| PSC | C211 — Architect - Engineer Services (including landscaping, interior layout, and designing) |
| Parent award / vehicle | 69056721D000006 |
| Set-aside | Not reported |
| Pricing type | LABOR HOURS |
| Obligations | $66.2K |
| Current contract value | $66.2K |
| Potential contract value / ceiling | $66.2K |
| Start date | Nov 30, 2023 |
| Current end date | Aug 2, 2025 |
| Potential end date | Aug 2, 2025 |
| Latest award activity | May 14, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 10 of 10 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 14, 2026 | P00009 | $-20.8K | OR FLAP UMATILL 582(1), MILL CREEK ROAD THIS MODIFICATION IS TO DE-OBLIGATE AND CLOSE OUT THE TASK ORDER. |
| Mar 20, 2025 | P00008 | $0 | OR FLAP UMATILL 582(1), MILL CREEK ROAD ADJUSTS HOURS TO MEET THE CURRENT NEEDS |
| Sep 13, 2024 | P00007 | $19.9K | OR FLAP UMATILL 582(1), MILL CREEK ROAD ADDS MORE HOURS FOR DESIGN SUPPORT OF THE CONSTRUCTION PROJECT |
| Aug 14, 2024 | P00006 | $0 | OR FLAP UMATILL 582(1), MILL CREEK ROAD REDISTRIBUTES HOURS AND UPDATES THE SUPPLIES RATE |
| Jun 20, 2024 | P00005 | $36.0K | OR FLAP UMATILL 582(1), MILL CREEK ROAD ADDS FUNDING TO VARIOUS LABOR CLASSIFICATIONS |
| Jun 7, 2024 | P00004 | $0 | OR FLAP UMATILL 582(1), MILL CREEK ROAD SHIFTS FUNDING TO VARIOUS LABOR CLASSIFICATION |
| May 30, 2024 | P00003 | $11.5K | OR FLAP UMATILL 582(1), MILL CREEK ROAD ADDS FUNDING TO VARIOUS LABOR CLASSIFICATIONS AND ADDS THE FOLLOWING LABOR CLASSIFICATIONS, CAD OPERATOR & TECHNICAL EDITOR |
| Apr 18, 2024 | P00002 | $0 | OR FLAP UMATILL 582(1), MILL CREEK ROAD ADJUSTS CLASSIFICATIONS HOURS |
| Dec 18, 2023 | P00001 | $0 | OR FLAP UMATILL 582(1), MILL CREEK ROAD REALLOCATES FUNDING CLASSIFICATIONS |
| Nov 30, 2023 | 0 | $19.6K | OR FLAP UMATILL 582(1), MILL CREEK ROAD ENGINEERING SUPPORT DURING ADVERTISEMENT AND CONSTRUCTION |