Federal contract award

693C7323C000016

PROJECT NC NP BLRI 2A16 THE PROJECT CONSISTS OF THE REHABILITATION OF BIG PINE CREEK BRIDGE #6, BIG PINE CREEK BRIDGE #3, AND BRUSH CREEK BRIDGE #1 BETWEEN MM 223.00 AND MM 228.00. THE WORK INCLUDES REHABILITATION OF THE SUBSTRUCTURE AND SUPERSTRUC

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Transportation
Office693C73 EASTERN FED LANDS DIVISION
NAICS237310 — Highway, Street, and Bridge Construction
PSCY1LB — CONSTRUCTION OF HIGHWAYS, ROADS, STREETS, BRIDGES, AND RAILWAYS
Parent award / vehicleNot reported
Set-asideSMALL BUSINESS SET ASIDE - TOTAL
Pricing typeFIRM FIXED PRICE
Obligations$13.6M
Current contract value$13.6M
Potential contract value / ceiling$13.6M
Start dateAug 31, 2023
Current end dateDec 31, 2027
Potential end dateDec 31, 2027
Latest award activityNov 18, 2025
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 5 of 5 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Nov 18, 2025P00004$0NC NP-BLRI 2A16 693C7323C000016 CM #4 NO CHANGE TO CONTRACT AMOUNT NO CHANGE TO CONTRACT TIME EXTEND PERIOD OF PERFORMANCE TO DECEMBER 31, 2027
Jul 17, 2025P00003$1.3MNP-BLRI 2A16 693C7323C000016 CM #3 INCREASE CONTRACT AMOUNT BY $1,328,384.00 EXTEND CONTRACT TIME TO JULY 25, 2025
Jan 7, 2025P00002$1.3MNP-BLRI 2A16 693C7323C000016 CM #2 INCREASE CONTRACT AMOUNT BY $1,275,850.00 EXTEND CONTRACT TIME BY 215 CALENDAR DAYS
Jan 4, 2024P00001$0NP-BLRI 2A16 693C7323C000016 CM #1 NO CHANGE TO CONTRACT AMOUNT NO CHANGE TO CONTRACT TIME EXTEND PERIOD OF PERFORMANCE TO DECEMBER 31, 2025
Aug 31, 20230$11.0MPROJECT NC NP BLRI 2A16 THE PROJECT CONSISTS OF THE REHABILITATION OF BIG PINE CREEK BRIDGE #6, BIG PINE CREEK BRIDGE #3, AND BRUSH CREEK BRIDGE #1 BETWEEN MM 223.00 AND MM 228.00. THE WORK INCLUDES REHABILITATION OF THE SUBSTRUCTURE AND SUPERSTRUC

Estimated positioning window

Dec 31, 2026 – Jun 30, 2027

Recompete signal:
70/100

Why this recompete signal

Contract timing and recorded acquisition signals at the time of calculation.

Stored score: 70/100. Available recorded signals: 65 points.

Contract end 2027-12-31 (432 days from calculation)
+25 points
221 historical awards in this buyer and category group
+15 points
5 recorded award transactions
+10 points
Latest award action: 2025-11-18
+5 points
Parent award identifier recorded
+0 points
Solicitation identifier recorded
+10 points
Linked official forecast
+0 points
Calculated on
2026-10-25 10:18:04.631876+00:00

The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.

Rule-based research score; it does not measure your chance of winning.

This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.

USAspending award record

. Rule-based research score; positioning dates are estimates.

Recompete score calculated Oct 25, 2026.

Research next steps

  1. Check the linked forecast or SAM for a confirmed solicitation and current timing.
  2. Check the stated set-aside against the solicitation and current certifications.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.