693C7324C000008
PROJECT FW-TREM 10(1): THE PROJECT CONSISTS OF GRADING, ROADWAY OBLITERATION, AGGREGATE BASE, AGGREGATE SURFACE COURSE, ASPHALT CONCRETE PAVEMENT, PORTLAND CEMENT CONCRETE PAVEMENT, PRECAST REINFORCED CONCRETE BOX CULVERTS, HELICAL PILES, STRUCTURAL
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Transportation |
| Office | 693C73 EASTERN FED LANDS DIVISION |
| NAICS | 237310 — Highway, Street, and Bridge Construction |
| PSC | Y1LB — CONSTRUCTION OF HIGHWAYS, ROADS, STREETS, BRIDGES, AND RAILWAYS |
| Parent award / vehicle | Not reported |
| Set-aside | SMALL BUSINESS SET ASIDE - TOTAL |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $3.5M |
| Current contract value | $3.5M |
| Potential contract value / ceiling | $3.5M |
| Start date | Apr 18, 2024 |
| Current end date | Aug 6, 2025 |
| Potential end date | Aug 6, 2025 |
| Latest award activity | Feb 10, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 3 of 3 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Feb 10, 2026 | P00004 | $0 | FW-TREM 10(1) THE PURPOSE OF THIS NO COST ADMINISTRATIVE MODIFICATION IS TO CLOSE THIS CONTRACT CONTRACTUALLY AND FINANCIALLY IN THE TOTAL AMOUNT OF $3,541,915.19. |
| Jul 30, 2025 | P00003 | $-61.2K | FW-TREM 10(1) CM #3 DECREASE CONTRACT AMOUNT BY -$61,228.18 NO CHANGE TO CONTRACT TIME |
| Apr 24, 2025 | P00002 | $121.6K | FW-TREM 10(1) CM #2 INCREASE CONTRACT AMOUNT BY $121,609.95 NO CHANGE TO CONTRACT TIME |