Federal contract award

693C7325F00075N

PROJECT NC ERFO NP BLRI 2024-1(5) THE PROJECT CONSISTS OF SLIDE REPAIRS, CULVERT REPLACEMENT, STONE MASONRY HEADWALL REPAIR, PAVEMENT RECONSTRUCTION, PAVEMENT MARKINGS AND OTHER MISCELLANEOUS WORK.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Transportation
Office693C73 EASTERN FED LANDS DIVISION
NAICS237310 — Highway, Street, and Bridge Construction
PSCY1LB — CONSTRUCTION OF HIGHWAYS, ROADS, STREETS, BRIDGES, AND RAILWAYS
Parent award / vehicle693C7320D000015
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$6.6M
Current contract value$6.6M
Potential contract value / ceiling$6.6M
Start dateMay 27, 2025
Current end dateJul 31, 2028
Potential end dateJul 31, 2028
Latest award activityJun 3, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 5 of 5 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jun 3, 2026P00004$0NC ERFO NP BLRI 2024-1(5) - CM #4: 693C7320D000015/693C7325F00075N THE PURPOSE OF THIS CONTRACT MODIFICATION IS TO: 1) EXTEND THE PERIOD OF PERFORMANCE FOR NC ERFO NP BLRI 2024-1(5) TO JULY 31, 2028. ALL OTHER TERMS AND CONDITIONS REMAIN THE U
May 11, 2026P00003$-1.6MNC ERFO NP BLRI 2024-1(5) - CM #3: 693C7320D000015/693C7325F00075N THE PURPOSE OF THIS CONTRACT MODIFICATION IS TO: 1) DECREASE CONTRACT AMOUNT BY $1,583,376.50 FROM $8,221,300.00 TO $6,637,923.50. 2) EXECUTE A DEDUCTIVE CHANGE UNDER THE CONTRAC
Jan 2, 2026P00002$974.0KNC ERFO NP BLRI 2024-1(5) - CM #2: 693C7320D000015/693C7325F00075N THE PURPOSE OF THIS CONTRACT MODIFICATION IS TO: 1) INCREASE CONTRACT AMOUNT BY $974,000.00. 2) EXTEND CONTRACT TIME BY 132 DAYS. 3) ADD THREE NEW PAY ITEMS. ALL OTHER TERMS
May 29, 2025P00001$0PROJECT NC ERFO NP BLRI 2024-1(5) THE PURPOSE OF THIS NO-COST, ADMINISTRATIVE MODIFICATION IS TO CORRECT THE CONTRACT NUMBER LISTED ON THE COVER PAGE OF THE TASK ORDER BOOK. THE CORRECT CONTRACT NUMBER IS 693C73-20-D-000015. ALL OTHER TERMS AND
May 27, 20250$7.2MPROJECT NC ERFO NP BLRI 2024-1(5) THE PROJECT CONSISTS OF SLIDE REPAIRS, CULVERT REPLACEMENT, STONE MASONRY HEADWALL REPAIR, PAVEMENT RECONSTRUCTION, PAVEMENT MARKINGS AND OTHER MISCELLANEOUS WORK.

Estimated positioning window

Jul 31, 2027 – Jan 31, 2028

Recompete signal:
75/100

Why this recompete signal

Contract timing and recorded acquisition signals at the time of calculation.

Stored score: 75/100. Available recorded signals: 70 points.

Contract end 2028-07-31 (645 days from calculation)
+25 points
221 historical awards in this buyer and category group
+15 points
5 recorded award transactions
+10 points
Latest award action: 2026-06-03
+5 points
Parent award identifier recorded
+5 points
Solicitation identifier recorded
+10 points
Linked official forecast
+0 points
Calculated on
2026-10-25 10:18:04.631876+00:00

The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.

Rule-based research score; it does not measure your chance of winning.

This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.

USAspending award record

. Rule-based research score; positioning dates are estimates.

Recompete score calculated Oct 25, 2026.

Research next steps

  1. Check the linked forecast or SAM for a confirmed solicitation and current timing.
  2. Confirm the ordering vehicle and your eligibility or a qualified teaming route.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.