Federal contract award
693JJ318F000007
TASK ORDER (TO) # 693JJ318F000007 IS ESTABLISHED BETWEEN THE DEPARTMENT OF TRANSPORTATION (DOT), FEDERAL HIGHWAY ADMINISTRATION (FHWA) AND THE SES GROUP. THIS TO WILL PROVIDE FUNDING FOR THE SES GROUP TO PROVIDE SUPPORT TO FHWA IN ACCORDANCE WITH THE ATTACHED PERFORMANCE WORK STATEMENT (PWS).
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Transportation |
| Office | 693JJ3 ACQUISITION AND GRANTS MGT |
| NAICS | 541712 |
| PSC | AB96 — OTHER COMMUNITY SERVICES AND DEVELOPMENT - MANAGEMENT AND SUPPORT |
| Parent award / vehicle | DTFH6117D00017 |
| Set-aside | Not reported |
| Pricing type | COST PLUS FIXED FEE |
| Obligations | $4.2M |
| Current contract value | $4.9M |
| Potential contract value / ceiling | $5.1M |
| Start date | Dec 1, 2017 |
| Current end date | Jul 31, 2023 |
| Potential end date | Jul 31, 2023 |
| Latest award activity | Jun 30, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 20 of 20 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jun 30, 2026 | P00019 | $-35.1K | CLOSEOUT AND DE-OBLIGATION OF FUNDS |
| Jul 12, 2023 | P00018 | $320.1K | ADD $320K INCREMENTAL FUNDING AND TIME EXTENSION OF IML TASK #693JJ318F000007 (PTF) THROUGH 7/31/23 |
| Apr 26, 2023 | P00017 | $145.0K | TIME EXTENSION THROUGH 5/31/23 AND $145K IN ADDED FUNDING |
| Mar 27, 2023 | P00016 | $0 | NO-COST EXTENSION OF IML TASK #693JJ318F000007 THROUGH 4/30/23 |
| Nov 23, 2022 | P00015 | $70.0K | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE OF THE TASK ORDER, ADD THE POSITION: PAVEMENT TEST FACILITY LAB MANAGER (PTF LM), AND ADD FUNDING IN THE AMOUNT OF $70,000.00. THE MODIFICATION HEREBY: 1) ADD THE POSITION: PA |
| Mar 22, 2022 | P00014 | $-757.0K | DEOBLIGATE FUNDING FROM PTF TASK #693JJ318F000007. |
| Jan 14, 2022 | P00013 | $0 | CORRECT ADMINISTRATIVE ERROR IN CONTRACT WRITING SYSTEM TO SHOW CORRECT TOTAL CONTRACT VALUE. |
| May 7, 2021 | P00012 | $846.0K | THE PURPOSE OF THIS MODIFICATION IS TO: 1. INCREASE THE CONSULTANT II POSITION AT NO ADDITIONAL COST TO THE GOVERNMENT. CONSULTANT II IS HEREBY INCREASED: FROM: ONE (1) CONSULTANT II TO: TWO (2) CONSULTANT II THE LEVEL OF EFFORT SHALL NOT |
| Apr 13, 2021 | P00011 | $400.0K | THE PURPOSE OF THIS MODIFICATION IS TO: 1. PROVIDE INCREMENTAL FUNDING TO CLIN 00007 IN THE AMOUNT OF $400,000.00; 2. THE TOTAL OBLIGATED TO THIS TASK ORDER IS INCREASED: FROM: $3,186,030.29 BY: $400,000.00 TO: $3,586,030.29 |
| Oct 9, 2020 | P00009 | $0 | THE PURPOSE OF THIS NO ADDITIONAL COST MODIFICATION IS TO INCREASE THE SUPPORT LABOR (SL) POSITION: FROM: ONE REQUIRED TO: TWO REQUIRED THE CONTRACTOR AGREES THERE ARE SUFFICIENT FUNDS CURRENTLY ON THE TASK ORDER TO FUND THE ADDITIONAL SL. |
| Oct 9, 2020 | P00010 | $0 | THE PURPOSE OF THIS NO ADDITIONAL COST MODIFICATION IS TO INCREASE THE SUPPORT LABOR (SL) POSITION: FROM: ONE REQUIRED TO: TWO REQUIRED THE CONTRACTOR AGREES THERE ARE SUFFICIENT FUNDS CURRENTLY ON THE TASK ORDER TO FUND THE ADDITIONAL SL. |
| Aug 19, 2020 | P00008 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO CHANGE THE TASK ORDER CONTRACTING OFFICER'S REPRESENTATIVE (TOCOR) TO MIKE ADAMS. |
| Aug 17, 2020 | P00007 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO: 1. REMOVE THE PAVEMENT TEST FACILITY (PTF) OPERATIONS ENGINEER AND ALL REQUIREMENTS FOR THIS POSITION; 2. ADD THE PTF LEAD ENGINEERING TECHNICIAN IN ACCORDANCE WITH THE POSITION DESCRIPTION LISTED IN EXHIBI |
| Aug 4, 2020 | P00006 | $1.1M | THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING IN THE AMOUNT OF $1,150,000.00 IN ACCORDANCE WITH FAR 52.232-22 - LIMITATION OF FUNDS. THIS TASK ORDER IS HEREBY FUNDED: FROM: $2,036,030.29 BY: $1,150,000.00 TO: $3,186,03 |
| Sep 3, 2019 | P00005 | $250.0K | THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING IN THE AMOUNT OF $250,000.00 IN ACCORDANCE WITH FAR 52.232-22 - LIMITATION OF FUNDS. THIS TASK ORDER IS HEREBY FUNDED: FROM: $1,786,030.29 BY: $250,000.00 TO: $2,036,030.29 |
| Mar 8, 2019 | P00004 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO CORRECT THE OBLIGATED AMOUNT. THE OBLIGATED IS HEREBY CORRECTED: FROM: $1,581,862.29 BY: $204,168.00 TO: $1,786,030.29 |
| Feb 28, 2019 | P00003 | $204.2K | THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE FUNDING IN THE AMOUNT OF $204,168.00 IN ACCORDANCE WITH FAR 52.232-22 - LIMITATION OF FUNDS. THIS TASK ORDER IS HEREBY FUNDED: FROM: $2,958,784.99 BY: $204,168.00 TO: $3,162,952.99 |
| Jun 6, 2018 | P00002 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO DELETE THE "PROGRESS REPORT ON ACHIEVEMENTS MADE FOR EACH PROJECT (NOT TO EXCEED 6 PAGES)" DELIVERABLE. |
| Apr 19, 2018 | P00001 | $941.8K | THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE FUNDING IN ACCORDANCE WITH FAR 52.232-22 - LIMITATION OF FUNDS. FUNDING IS HEREBY PROVIDED IN THE AMOUNT OF $941,822.29. THE TOTAL OBLIGATED TO THIS TASK ORDER IS INCREASED: FROM: $640,040.00 BY: $941,822.29 TO: $1,581,862.29 |
| Nov 29, 2017 | 0 | $640.0K | TASK ORDER (TO) # 693JJ318F000007 IS ESTABLISHED BETWEEN THE DEPARTMENT OF TRANSPORTATION (DOT), FEDERAL HIGHWAY ADMINISTRATION (FHWA) AND THE SES GROUP. THIS TO WILL PROVIDE FUNDING FOR THE SES GROUP TO PROVIDE SUPPORT TO FHWA IN ACCORDANCE WITH THE ATTACHED PERFORMANCE WORK STATEMENT (PWS). |