| Field | Reported value |
|---|---|
| Agency | Department of Transportation |
| Office | 693JJ6 FEDERAL RAILROAD ADMIN |
| NAICS | 541330 — Engineering Services |
| PSC | R425 — Engineering and Technical Services |
| Parent award / vehicle | 693JJ624A000001 |
| Set-aside | Not reported |
| Pricing type | LABOR HOURS |
| Obligations | $3.5M |
| Current contract value | $3.6M |
| Potential contract value / ceiling | $11.0M |
| Start date | Aug 15, 2025 |
| Current end date | Oct 16, 2026 |
| Potential end date | Oct 16, 2026 |
| Latest award activity | Sep 3, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 4 of 4 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Sep 3, 2026 | P00004 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE BASE PERIOD OF PERFORMANCE USING CLAUSE FAR 52.217-8 |
| Jul 24, 2026 | P00003 | $0 | MODIFICATION TO INCORPORATE LCATS, CHANGE FRA CORS & COS, AND ADD NEW TAR CLAUSE |
| Dec 15, 2025 | P00001 | $0 | THE PURPOSE OF THIS UNILATERAL ADMINISTRATIVE MODIFICATION IS TO CHANGE THE PRIMARY COR TO ANDREW PETERNITH AND THE ALTERNATE COR TO KELSEY COOPER. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. |
| Aug 15, 2025 | 0 | $3.5M | U.S. DEPARTMENT OF TRANSPORTATION (DOT), FEDERAL RAILROAD ADMINISTRATION (FRA), OFFICE OF ACQUISITION (RAD-30) IN SUPPORT OF THE OFFICE OF RAILROAD DEVELOPMENT (RRD) FOR A BPA ORDER FOR SUPPORT, TECHNICAL, OVERSIGHT, REVIEW, MONITORING (STORM) THAT S |
Research next steps
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.