Federal contract award
693KA921F00075
PROVIDE FUNDING FOR ERAM ENHANCEMENTS 2 SUPPORT (ERAM PROGRAM OFFICE SUPPORT FOR ERAM ADS-B IN OPERATIONAL USE CASE AND PHASE 1 FID)
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Transportation |
| Office | 693KA9 CONTRACTING FOR SERVICES |
| NAICS | 541330 — Engineering Services |
| PSC | R408 — Program Management/Support Services |
| Parent award / vehicle | 693KA921D00004 |
| Set-aside | Not reported |
| Pricing type | TIME AND MATERIALS |
| Obligations | $10.9M |
| Current contract value | $10.9M |
| Potential contract value / ceiling | $13.6M |
| Start date | Sep 23, 2021 |
| Current end date | Sep 30, 2026 |
| Potential end date | Sep 30, 2026 |
| Latest award activity | Jun 25, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 20 of 20 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jun 25, 2026 | P00019 | $0 | MOD 19 / INCORPORATING IAW AMS CLAUSE 3.10.1-28 CHANGES REQUIRED BY AMS |
| Sep 19, 2025 | P00018 | $0 | MOD 18 / EXERCISE OPTION 4 / NO COST |
| Dec 19, 2024 | P00017 | $0 | MOD 17 / CHANGE ORDER - REDUCE TASK VALUE / F&E TYPE FUNDS / TASK TITLE: EN ROUTE AUTOMATION MODERNIZATION (ERAM) - AJM 213 - ENHANCEMENTS 2 AND ENHANCMENTS 3 - PROGRAM OFFICE SUPPORT FOR ERAM ADS-B IN OPERATIONAL USE CASE AND PHASE 1 FID) |
| Dec 12, 2024 | P00016 | $975.0K | MOD 16 / PR WA-25-05-01638 / $975,000.00 / INCREMENTAL FUNDING / F&E TYPE FUNDS / TASK TITLE: EN ROUTE AUTOMATION MODERNIZATION (ERAM) - AJM 213 - ENHANCEMENTS 2 AND ENHANCMENTS 3 - PROGRAM OFFICE SUPPORT FOR ERAM ADS-B IN OPERATIONAL USE CASE AN |
| Jul 30, 2024 | P00015 | $1.1M | MOD 15 / PR WA-24-05705 / $1,117,448.95 / INCREMENTAL FUNDING / F&E TYPE FUNDS / TASK TITLE: EN ROUTE AUTOMATION MODERNIZATION (ERAM) - AJM 213 - ENHANCEMENTS 2 AND ENHANCMENTS 3 - PROGRAM OFFICE SUPPORT FOR ERAM ADS-B IN OPERATIONAL USE CASE AND |
| Jul 23, 2024 | P00014 | $465.0K | MOD 14 / EXERCISE OPTION THREE & INCREMENTAL FUNDING / MULTIPLE PR'S / F&E TYPE FUNDS/ INCREMENTAL FUNDING MOD / TASK TITLE: EN ROUTE AUTOMATION MODERNIZATION (ERAM) - AJM 213 - ENHANCEMENTS 2 AND ENHANCMENTS 3 - PROGRAM OFFICE SUPPORT F |
| May 8, 2024 | P00013 | $600.0K | MOD 13/ PRWA-24-03624 000001/ $600,000.00/ F&E TYPE FUNDS/ INCREMENTAL FUNDING MOD / TASK TITLE: EN ROUTE AUTOMATION MODERNIZATION (ERAM) - AJM 213 - ENHANCEMENTS 2 AND ENHANCMENTS 3 - PROGRAM OFFICE SUPPORT FOR ERAM ADS-B IN OPERATIONAL USE CASE |
| Apr 26, 2024 | P00012 | $1.2M | MOD 12/ PR WA-24-05702 / $1,238,714.07 / F&E TYPE FUNDS / INCREMENTAL FUNDING MOD / TASK TITLE: EN ROUTE AUTOMATION MODERNIZATION (ERAM) - AJM 213 - ENHANCEMENTS 2 AND ENHANCMENTS 3 - PROGRAM OFFICE SUPPORT FOR ERAM ADS-B IN OPERATIONAL USE CASE |
| Mar 28, 2024 | P00011 | $383.1K | MOD 11 / PR WA-24-04261 / $383,150.00 F&E TYPE FUNDS / INCREMENTAL FUNDING MOD / TASK TITLE: EN ROUTE AUTOMATION MODERNIZATION (ERAM) - AJM 213 - ENHANCEMENTS 2 AND ENHANCMENTS 3 - PROGRAM OFFICE SUPPORT FOR ERAM ADS-B IN OPERATIONAL USE CASE AND |
| Feb 27, 2024 | P00010 | $0 | MOD 10/ CHANGE ORDER - REDUCE TASK VALUE & REVISE TASK SCOPE / F&E TYPE FUNDS /-PSS/ F&E TYPE FUNDS /TASK TITLE: EN ROUTE AUTOMATION MODERNIZATION (ERAM) -AJM 213 - ENHANCEMENTS 2 AND ENHANCEMENTS 3 -PSS / ERAM ENHANCEMENTS 2 SUPPORT (ERA |
| Sep 13, 2023 | P00009 | $1.2M | MOD 9 / PR WA-23-09741 /$1,154,000.00/ F&E TYPE FUNDS /TASK TITLE: EN ROUTE AUTOMATION MODERNIZATION (ERAM) -AJM 213 - ENHANCEMENTS 2 AND ENHANCEMENTS 3 -PSS / ERAM ENHANCEMENTS 2 SUPPORT (ERAM PROGRAM OFFICE SUPPORT FOR ERAM ADS-B IN OPERATIONAL |
| Aug 16, 2023 | P00008 | $499.6K | MOD 8 / PR WA-23-07550 /$499,602.66/ F&E TYPE FUNDS /TASK TITLE: EN ROUTE AUTOMATION MODERNIZATION (ERAM) -AJM 213 - ENHANCEMENTS 2 AND ENHANCEMENTS 3 -PSS / ERAM ENHANCEMENTS 2 SUPPORT (ERAM PROGRAM OFFICE SUPPORT FOR ERAM ADS-B IN OPERATIONAL U |
| Jul 27, 2023 | P00007 | $0 | MOD 7/ EXERCISE OPT 2 / /TASK TITLE: EN ROUTE AUTOMATION MODERNIZATION (ERAM) -AJM 213 - ENHANCEMENTS 2 AND ENHANCEMENTS 3 -PSS / ERAM ENHANCEMENTS 2 SUPPORT (ERAM PROGRAM OFFICE SUPPORT FOR ERAM ADS-B IN OPERATIONAL USE CASE AND PHASE 1 FID) |
| May 2, 2023 | P00006 | $801.1K | MOD 6/ PR WA-23-04738/ $801,114.00 /F&E/INCREMENTAL FUNDS /TASK TITLE: EN ROUTE AUTOMATION MODERNIZATION (ERAM) -AJM 213 - ENHANCEMENTS 2 AND ENHANCEMENTS 3 -PSS/ ERAM ENHANCEMENTS 2 SUPPORT (ERAM PROGRAM OFFICE SUPPORT FOR ERAM ADS-B IN OPERATIO |
| Feb 17, 2023 | P00005 | $414.4K | MOD 5/ PR WA-23-02798/ $414,444.00 /F&E/INCREMENTAL FUNDS /TASK TITLE: EN ROUTE AUTOMATION MODERNIZATION (ERAM) -AJM 213 - ENHANCEMENTS 2 AND ENHANCEMENTS 3 -PSS/ ERAM ENHANCEMENTS 2 SUPPORT (ERAM PROGRAM OFFICE SUPPORT FOR ERAM ADS-B IN OPERATIO |
| Aug 23, 2022 | P00004 | $1.4M | MOD 4 / EXCERCISE OPTION ONE & PROVIDE INCREMENTAL FUNDS / ERAM ENHANCEMENTS 2 SUPPORT (ERAM PROGRAM OFFICE SUPPORT FOR ERAM ADS-B IN OPERATIONAL USE CASE AND PHASE 1 FID) |
| Jun 27, 2022 | P00003 | $300.0K | MOD 3 / INCREMENTAL FUNDS / ERAM ENHANCEMENTS 2 SUPPORT (ERAM PROGRAM OFFICE SUPPORT FOR ERAM ADS-B IN OPERATIONAL USE CASE AND PHASE 1 FID) |
| Dec 8, 2021 | P00002 | $687.4K | PROVIDE FUNDING FOR ERAM ENHANCEMENTS 2 SUPPORT (ERAM PROGRAM OFFICE SUPPORT FOR ERAM ADS-B IN OPERATIONAL USE CASE AND PHASE 1 FID) |
| Sep 24, 2021 | P00001 | $0 | PROVIDE FUNDING FOR ERAM ENHANCEMENTS 2 SUPPORT (ERAM PROGRAM OFFICE SUPPORT FOR ERAM ADS-B IN OPERATIONAL USE CASE AND PHASE 1 FID) |
| Sep 23, 2021 | 0 | $882.1K | PROVIDE FUNDING FOR ERAM ENHANCEMENTS 2 SUPPORT (ERAM PROGRAM OFFICE SUPPORT FOR ERAM ADS-B IN OPERATIONAL USE CASE AND PHASE 1 FID) |
Research next steps
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.