Federal contract award

6973GH19F00563

ACEPS TYPE II PHASE 1 SITE SPECIFIC DESIGN, CPC REDUCTION AND INSTALLATION FOR THE KANSAS CITY ARTCC

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Transportation
Office6973GH FRANCHISE ACQUISITION SVCS
NAICS238210 — Electrical Contractors and Other Wiring Installation Contractors
PSCN061 — Installation of Equipment: Electric Wire, and Power and Distribution Equipment
Parent award / vehicleDTFAAC16D00019
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$12.1M
Current contract value$12.1M
Potential contract value / ceiling$12.1M
Start dateFeb 26, 2019
Current end dateJun 30, 2026
Potential end dateSep 30, 2026
Latest award activityMay 11, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 11 of 11 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
May 11, 2026P00010$405.3KCHANGE ORDER FOR WELLS GLOBAL TO PROVIDE ALL NECESSARY LABOR, TOOLS, AND MATERIALS TO DESIGN AND EXECUTE THE CPC-D REMOVAL AND REPLACEMENT WITH A WELLS GLOBAL SUPPLIED 112.5 KVA TRANSFORMER, ENSURING COMPLIANCE WITH FAA STANDARDS AND LOCAL CODES. SEC
Jan 23, 2026P00009$233.3KCHANGE ORDER TO FUND THE COSTS ASSOCIATED WITH THE DE-MOBILIZATION/RE-MOBILIZATION CAUSED BY THE OCTOBER/NOVEMBER 2025 GOVERNMENT SHUTDOWN AT THE ZKC ARTCC. ALSO, TO CHANGE THE CONTRACTING OFFICER FROM DAMION NOIEL TO AMANDA GAREN AND UPDATE THE DAVI
Sep 24, 2025P00008$489.3KACEPS TYPE II PHASE 1 SITE SPECIFIC DESIGN, CPC REDUCTION AND INSTALLATION FOR THE KANSAS CITY ARTCC
Jun 18, 2025P00007$21.8KACEPS TYPE II PHASE 1 SITE SPECIFIC DESIGN, CPC REDUCTION AND INSTALLATION FOR THE KANSAS CITY ARTCC
May 19, 2025P00006$77.5KACEPS TYPE II PHASE 1 SITE SPECIFIC DESIGN, CPC REDUCTION AND INSTALLATION FOR THE KANSAS CITY ARTCC
Apr 25, 2025P00005$15.3KACEPS TYPE II PHASE 1 SITE SPECIFIC DESIGN, CPC REDUCTION AND INSTALLATION FOR THE KANSAS CITY ARTCC
Aug 12, 2024P00004$150.6KACEPS TYPE II PHASE 1 SITE SPECIFIC DESIGN, CPC REDUCTION AND INSTALLATION FOR THE KANSAS CITY ARTCC
Sep 11, 2023P00003$4.4MACEPS TYPE II PHASE 1 SITE SPECIFIC DESIGN, CPC REDUCTION AND INSTALLATION FOR THE KANSAS CITY ARTCC
Jun 8, 2020P00002$2.5KACEPS TYPE II PHASE 1 SITE SPECIFIC DESIGN, CPC REDUCTION AND INSTALLATION FOR THE KANSAS CITY ARTCC
May 23, 2019P00001$102.4KACEPS TYPE II PHASE 1 SITE SPECIFIC DESIGN, CPC REDUCTION AND INSTALLATION FOR THE KANSAS CITY ARTCC
Feb 26, 20190$6.2MACEPS TYPE II PHASE 1 SITE SPECIFIC DESIGN, CPC REDUCTION AND INSTALLATION FOR THE KANSAS CITY ARTCC

Research next steps

  1. Verify whether remaining options may extend performance beyond the current end date.
  2. Confirm the ordering vehicle and your eligibility or a qualified teaming route.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.