Federal contract award
6973GH22F01626
BIL FUNDING FOR SITE SURVEY, DESIGN, AND EG INSTALLATION AT STAMPEDE PASS, WA (SMP) RCLR JCN:18063568
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Transportation |
| Office | 6973GH FRANCHISE ACQUISITION SVCS |
| NAICS | 238210 — Electrical Contractors and Other Wiring Installation Contractors |
| PSC | N059 — Installation of Equipment: Electrical and Electronic Equipment Components |
| Parent award / vehicle | 6973GH22D00009 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $528.8K |
| Current contract value | $528.8K |
| Potential contract value / ceiling | $528.8K |
| Start date | Sep 6, 2022 |
| Current end date | Dec 31, 2025 |
| Potential end date | Dec 31, 2025 |
| Latest award activity | Nov 14, 2025 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 4 of 4 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Nov 14, 2025 | P00003 | $4.9K | IIJA FUNDS. CHANGE ORDER FOR TO PROVIDE A CREDIT FOR REUSING THE ATS PAD AND TO FUND THE COSTS RELATED TO THE REHLKO STARTUP DELAY AT STAMPEDE PASS, WA (SMP) RCLR. JCN: 18063568 |
| Jul 17, 2025 | P00002 | $133.4K | IIJA FUNDS. SITE-SPECIFIC INSTALLATION COST PRICING TO REMOVE THE EXISTING 10KW EG AND ALL ITS ASSOCIATED PARTS AND REPLACE WITH A 25KW EG 240/120V, 1PH IAW THE APPROVED DRAWINGS DATED 5/22/2025 AND THE 2022 125KW EG INDOOR BASELINE, REMOVE THE EXIST |
| Aug 16, 2024 | P00001 | $133.5K | BIL FUNDING. CHANGE ORDER TO ADD THE 2024 FST PROPANE BASELINE DESIGN AND INSTALLATION PRICES TO THE STAMPEDE PASS, WA (SMP) RCLR. JCN: 18063568 |
| Sep 6, 2022 | 0 | $257.0K | BIL FUNDING FOR SITE SURVEY, DESIGN, AND EG INSTALLATION AT STAMPEDE PASS, WA (SMP) RCLR JCN:18063568 |
Research next steps
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.