Federal contract award

6973GH22F01676

BIL FUNDING FOR SITE SURVEY, DESIGN, AND EG INSTALLATION AND LPGBS AT MERCED, CA (MCE) ASR JCN:22001391 / LPGBS BIL JCN 1106231

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Transportation
Office6973GH FRANCHISE ACQUISITION SVCS
NAICS238210 — Electrical Contractors and Other Wiring Installation Contractors
PSCN059 — Installation of Equipment: Electrical and Electronic Equipment Components
Parent award / vehicle6973GH22D00009
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$522.2K
Current contract value$522.2K
Potential contract value / ceiling$522.2K
Start dateSep 12, 2022
Current end dateJun 30, 2026
Potential end dateJun 30, 2026
Latest award activityApr 14, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 5 of 5 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Apr 14, 2026P00004$27.7KIIJA FUNDS, CHANGE ORDER IS TO FUND THE COSTS ASSOCIATED WITH THE UTILITY AND CUTOVER DELAY FROM FEBRUARY 20, 2026 TO MARCH 14, 2026 AT MERCED, CA (MCE) ASR JCN:22001391
Mar 9, 2026P00003$1.6KIIJA FUNDS, THE PURPOSE OF THIS BILATERAL MODIFICATION IS TO TO COVER THE EXPENSES RELATED TO CNS SUPPLYING 304 GALLONS OF PROPANE FOR THE STARTUP PROCESS, AS WELL AS MODIFYING THE PANEL BOARD CONFIGURATION IN PANEL BOARD DP7 FROM TWO 20-AMP BREAKERS
Feb 26, 2026P00002$9.0KIIJA FUNDS, THE PURPOSE OF THIS BILATERAL MODIFICATION IS TO FUND THE PURCHASE AND INSTALLATION OF CB1 CONTROL WIRING. FURNISH AND INSTALL ONE WALL-MOUNTED GRAVITY INTAKE DAMPER WITH EXTERIOR HOOD IN ACCORDANCE WITH THE SCOPE OF WORK DATED 2/10/2026.
Dec 10, 2025P00001$188.9KIIJA FUNDS, SITE-SPECIFIC PRICING TO REMOVE THE EXISTING 135KW EG AND ALL ITS ASSOCIATED PARTS AND REPLACE WITH A 125KW EG 480Y/277V, 3PH IAW THE APPROVED DRAWINGS DATED 2/6/2025 AND THE 2022 125KW EG OUTDOOR BASELINE WITH ERMS INSTALLATION SOW, ER
Sep 12, 20220$295.0KBIL FUNDING FOR SITE SURVEY, DESIGN, AND EG INSTALLATION AND LPGBS AT MERCED, CA (MCE) ASR JCN:22001391 / LPGBS BIL JCN 1106231