BIL FUNDING FOR SITE SURVEY, DESIGN, EG INSTALLATION AND LPGBS FOR COVINGTON, KY (CVGC) ASR JCN:22001367 / LPGBS BIL JCN 1404499

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Transportation
Office6973GH FRANCHISE ACQUISITION SVCS
NAICS238210 — Electrical Contractors and Other Wiring Installation Contractors
PSCN059 — Installation of Equipment: Electrical and Electronic Equipment Components
Parent award / vehicle6973GH22D00016
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$530.8K
Current contract value$530.8K
Potential contract value / ceiling$530.8K
Start dateSep 12, 2022
Current end dateDec 31, 2025
Potential end dateDec 31, 2025
Latest award activityDec 10, 2025
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 4 of 4 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Dec 10, 2025P00003$29.6KIIJA FUNDS. CHANGE ORDER IS TO FUND COSTS ASSOCIATED WITH THE REHLKO DELAY FROM 8/12/2025 TO 8/26/2025.THIS MODIFICATION ALSO INCLUDES THE CREDIT FOR THE ONE SPD (PART NUMBER 120-2S-M3-3-06-A-H) PROVIDED TO URBAN ELECTRIC BY THE LPGBS PROGRAM OFFICE.
Jul 16, 2025P00002$187.7KIIJA FUNDS. SITE-SPECIFIC INSTALLATION COST TO REMOVE THE EXISTING 175KW EG AND ALL ITS ASSOCIATED PARTS AND REPLACE WITH A 200KW EG 120/208V, 3PH IAW THE APPROVED DRAWINGS DATED 1/28/2025 AND THE 2022 125KW EG OUTDOOR BASELINE AND A FULL POWER SYST
Nov 9, 2022P00001$3.5KBIL FUNDING FOR SITE SURVEY, DESIGN, EG INSTALLATION AND LPGBS FOR COVINGTON, KY (CVGC) ASR JCN:22001367 / LPGBS BIL JCN 1404499
Sep 12, 20220$310.1KBIL FUNDING FOR SITE SURVEY, DESIGN, EG INSTALLATION AND LPGBS FOR COVINGTON, KY (CVGC) ASR JCN:22001367 / LPGBS BIL JCN 1404499