Federal contract award

6973GH23F01841

BIL FUNDING FOR SITE SURVEY, DESIGN, AND INSTALLATION FOR EG PO LED POWER SYSTEM REPLACEMENT PROJECT FOR SALINA, KS (SLNC) ATCT JCN: 19003449

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Transportation
Office6973GH FRANCHISE ACQUISITION SVCS
NAICS238210 — Electrical Contractors and Other Wiring Installation Contractors
PSCN059 — Installation of Equipment: Electrical and Electronic Equipment Components
Parent award / vehicle6973GH22D00007
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$543.2K
Current contract value$543.2K
Potential contract value / ceiling$543.2K
Start dateSep 12, 2023
Current end dateOct 31, 2026
Potential end dateOct 31, 2026
Latest award activityJan 22, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 4 of 4 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jan 22, 2026P00003$25.1KIIJA FUNDS. EXTEND THE RENTAL PERIOD FOR THE EG TEMP POWER EQUIPMENT LEFT ON SITE BY AN ADDITIONAL TWO WEEKS DUE TO THE CHRISTMAS/NEW YEARS MORATORIUM. IT ALSO COVERS THE LABOR REQUIRED TO COMPLETE THE PROJECT, WHICH WAS DELAYED BY INCLEMENT WEATHER
Oct 24, 2025P00002$162.2KIIJA FUNDS. SITE-SPECIFIC PRICING TO REMOVE THE EXISTING 175KW EG AND ALL ITS ASSOCIATED PARTS AND REPLACE WITH A 200KW EG 208/120V, 3PH IAW THE APPROVED DRAWINGS DATED 7/7/2025 AND THE 2023 125KW EG OUTDOOR BASELINE WITH ERMS INSTALLATION SOW, ERMS
Dec 10, 2024P00001$2.3KBIL FUNDS. ADDING ADVANCED METERING INTO THE EG DESIGN FOR SALINA, KS (SLNC) ATCT JCN: 19003449
Sep 12, 20230$353.6KBIL FUNDING FOR SITE SURVEY, DESIGN, AND INSTALLATION FOR EG PO LED POWER SYSTEM REPLACEMENT PROJECT FOR SALINA, KS (SLNC) ATCT JCN: 19003449