Federal contract award

6973GH24F01195

BIL FUNDS. 2023 INDOOR EG BASELINE INSTALLATION AND ERMS FOR INDIANAPOLIS, IN (OQV) ALS JCN: 1400989

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Transportation
Office6973GH FRANCHISE ACQUISITION SVCS
NAICS238210 — Electrical Contractors and Other Wiring Installation Contractors
PSCN059 — Installation of Equipment: Electrical and Electronic Equipment Components
Parent award / vehicle6973GH22D00014
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$429.2K
Current contract value$429.2K
Potential contract value / ceiling$429.2K
Start dateJul 23, 2024
Current end dateSep 30, 2025
Potential end dateSep 30, 2025
Latest award activityFeb 5, 2025
Source loadedAug 15, 2026

Funding and modification history

Showing the latest 4 of 4 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Feb 5, 2025P00006$9.6KBIL FUNDS. CHANGE ORDER #6, EXTEND RENTAL OF TEMPORARY POWER EQUIPMENT ONSITE 30 DAYS DUE TO NEWLY INSTALLED EG ISSUE AND THE UPDATE ARC FLASH STUDY FROM 180 KW EG TO 200 KW EG DUE TO 2ND LEVEL SWAPPING EGS FOR INDIANAPOLIS, IN (OQV) ALS JCN: 140098
Dec 10, 2024P00005$14.8KBIL FUNDS. CHANGE ORDER #5, COSTS ASSOCIATED WITH THE EXTENDED TEMPORARY EG RENTAL FROM 11/8/2024 THOUGH 1/6/2025 WHILE THE EG PMO DECIDES THE PATH FORWARD TO FIX THE ISSUE WITH THE NEWLY INSTALLED EG AT THE INDIANAPOLIS, IN (OQV) ALS JCN: 1400989
Nov 19, 2024P00004$11.0KBIL FUNDS. CHANGE ORDER #5, CONTINUANCE OF TEMPORARY POWER RENTAL SO NEW EG CAN UNDERGO TESTING FOR INDIANAPOLIS, IN (OQV) ALS JCN: 1400989
Oct 18, 2024P00003$11.9KBIL FUNDS. CHANGE ORDER #4, PROVIDE AND INSTALL TEMPORARY POWER SO NEW EG CAN UNDERGO TESTING FOR INDIANAPOLIS, IN (OQV) ALS JCN: 1400989