Federal contract award

6973GH25C00070

*REPLACE THE ENTRY AND EXIT GATES AT THE ATL ATCT *REMOVE THE EXISTING QUARTZ FLOORING SYSTEM THAT IS INSTALLED ON THE EXTERIOR OF THE 2ND FLOOR BREAKROOM PATIO AND ATCT BREEZEWAY, AND REPLACE THE FLOORING SYSTEM WITH A SIMILAR IN-KIND ASSEMBLY

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Transportation
Office6973GH FRANCHISE ACQUISITION SVCS
NAICS236220 — Commercial and Institutional Building Construction
PSCZ2BA — REPAIR OR ALTERATION OF AIR TRAFFIC CONTROL TOWERS
Parent award / vehicleNot reported
Set-asideSMALL BUSINESS SET ASIDE - TOTAL
Pricing typeFIRM FIXED PRICE
Obligations$236.8K
Current contract value$236.8K
Potential contract value / ceiling$236.8K
Start dateFeb 18, 2025
Current end dateJul 23, 2025
Potential end dateJul 31, 2025
Latest award activityJun 23, 2025
Source loadedAug 15, 2026

Funding and modification history

Showing the latest 3 of 3 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jun 23, 2025P00002$5.4K*REPLACE THE ENTRY AND EXIT GATES AT THE ATL ATCT *REMOVE THE EXISTING QUARTZ FLOORING SYSTEM THAT IS INSTALLED ON THE EXTERIOR OF THE 2ND FLOOR BREAKROOM PATIO AND ATCT BREEZEWAY, AND REPLACE THE FLOORING SYSTEM WITH A SIMILAR IN-KIND ASSEMBLY
Mar 12, 2025P00001$0*REPLACE THE ENTRY AND EXIT GATES AT THE ATL ATCT *REMOVE THE EXISTING QUARTZ FLOORING SYSTEM THAT IS INSTALLED ON THE EXTERIOR OF THE 2ND FLOOR BREAKROOM PATIO AND ATCT BREEZEWAY, AND REPLACE THE FLOORING SYSTEM WITH A SIMILAR IN-KIND ASSEMBLY
Feb 18, 20250$231.5K*REPLACE THE ENTRY AND EXIT GATES AT THE ATL ATCT *REMOVE THE EXISTING QUARTZ FLOORING SYSTEM THAT IS INSTALLED ON THE EXTERIOR OF THE 2ND FLOOR BREAKROOM PATIO AND ATCT BREEZEWAY, AND REPLACE THE FLOORING SYSTEM WITH A SIMILAR IN-KIND ASSEMBLY

Research next steps

  1. Verify whether remaining options may extend performance beyond the current end date.
  2. Check the stated set-aside against the solicitation and current certifications.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.