Federal contract award

6973GH25C00168

THE SITE INCLUDES AN 8X16 FIBERGLASS EQUIPMENT SHELTER SUPPORTED BY A CONCRETE FOUNDATION, WOOD POST SERVICE DISCONNECT RACK AND A 50 KVA TRANSFORMER ON A CONCRETE PAD THAT WAS INSTALLED APPROXIMATELY 20 YEARS AGO. THE SITE IS EXPERIENCING POOR DRAIN

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Transportation
Office6973GH FRANCHISE ACQUISITION SVCS
NAICS238140 — Masonry Contractors
PSCZ2BA — REPAIR OR ALTERATION OF AIR TRAFFIC CONTROL TOWERS
Parent award / vehicleNot reported
Set-asideSMALL BUSINESS SET ASIDE - TOTAL
Pricing typeFIRM FIXED PRICE
Obligations$165.1K
Current contract value$165.1K
Potential contract value / ceiling$165.1K
Start dateAug 24, 2025
Current end dateFeb 25, 2026
Potential end dateFeb 25, 2026
Latest award activityFeb 24, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 7 of 7 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Feb 24, 2026P00006$0THE SITE INCLUDES AN 8X16 FIBERGLASS EQUIPMENT SHELTER SUPPORTED BY A CONCRETE FOUNDATION, WOOD POST SERVICE DISCONNECT RACK AND A 50 KVA TRANSFORMER ON A CONCRETE PAD THAT WAS INSTALLED APPROXIMATELY 20 YEARS AGO. THE SITE IS EXPERIENCING POOR DRAIN
Feb 19, 2026P00005$0THE SITE INCLUDES AN 8X16 FIBERGLASS EQUIPMENT SHELTER SUPPORTED BY A CONCRETE FOUNDATION, WOOD POST SERVICE DISCONNECT RACK AND A 50 KVA TRANSFORMER ON A CONCRETE PAD THAT WAS INSTALLED APPROXIMATELY 20 YEARS AGO. THE SITE IS EXPERIENCING POOR DRAIN
Jan 26, 2026P00004$120THE SITE INCLUDES AN 8X16 FIBERGLASS EQUIPMENT SHELTER SUPPORTED BY A CONCRETE FOUNDATION, WOOD POST SERVICE DISCONNECT RACK AND A 50 KVA TRANSFORMER ON A CONCRETE PAD THAT WAS INSTALLED APPROXIMATELY 20 YEARS AGO. THE SITE IS EXPERIENCING POOR DRAIN
Jan 20, 2026P00003$0THE SITE INCLUDES AN 8X16 FIBERGLASS EQUIPMENT SHELTER SUPPORTED BY A CONCRETE FOUNDATION, WOOD POST SERVICE DISCONNECT RACK AND A 50 KVA TRANSFORMER ON A CONCRETE PAD THAT WAS INSTALLED APPROXIMATELY 20 YEARS AGO. THE SITE IS EXPERIENCING POOR DRAIN
Oct 27, 2025P00002$0THE SITE INCLUDES AN 8X16 FIBERGLASS EQUIPMENT SHELTER SUPPORTED BY A CONCRETE FOUNDATION, WOOD POST SERVICE DISCONNECT RACK AND A 50 KVA TRANSFORMER ON A CONCRETE PAD THAT WAS INSTALLED APPROXIMATELY 20 YEARS AGO. THE SITE IS EXPERIENCING POOR DRAIN
Oct 24, 2025P00001$0THE SITE INCLUDES AN 8X16 FIBERGLASS EQUIPMENT SHELTER SUPPORTED BY A CONCRETE FOUNDATION, WOOD POST SERVICE DISCONNECT RACK AND A 50 KVA TRANSFORMER ON A CONCRETE PAD THAT WAS INSTALLED APPROXIMATELY 20 YEARS AGO. THE SITE IS EXPERIENCING POOR DRAIN
Aug 24, 20250$165.0KTHE SITE INCLUDES AN 8X16 FIBERGLASS EQUIPMENT SHELTER SUPPORTED BY A CONCRETE FOUNDATION, WOOD POST SERVICE DISCONNECT RACK AND A 50 KVA TRANSFORMER ON A CONCRETE PAD THAT WAS INSTALLED APPROXIMATELY 20 YEARS AGO. THE SITE IS EXPERIENCING POOR DRAIN

Research next steps

  1. Check the stated set-aside against the solicitation and current certifications.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.