Federal contract award

697DCK24C00063

ZMP ARTCC MECHANICAL AND ELECTRICAL UPGRADES - PREFERRED SDVOSB SET ASIDE

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Transportation
Office697DCK REGIONAL ACQUISITIONS SVCS
NAICS236220 — Commercial and Institutional Building Construction
PSCY1BG — CONSTRUCTION OF ELECTRONIC AND COMMUNICATIONS FACILITIES
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$714.8K
Current contract value$714.8K
Potential contract value / ceiling$714.8K
Start dateDec 12, 2023
Current end dateMar 31, 2026
Potential end dateMar 31, 2026
Latest award activityDec 4, 2025
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 8 of 8 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Dec 4, 2025P00007$11.6KMOD 7 TO ADD CREDIT FOR LI 00002
Aug 11, 2025P00006$0MOD 6 TO CHANGE CO AND CS EXTEND POP END DATE
Jan 15, 2025P00005$0MOD 5 TO CHANGE COR TO WILLIAM S. WAGNER
Jan 13, 2025P00004$-51.0KCOMPLETE RECLASS BY CANCELING LINE ITEM 2
Dec 20, 2024P00003$43.7KBASE - ZMP ARTCC MECHANICAL AND ELECTRICAL UPGRADES MODIFICATION NO. 3 RFQ 1 - REVISE OPERATING MODE OF HUMIDIFIERS - RFQ 3 - VARIOUS INSTALLATION REVISIONS ASSOCIATED WITH HUMIDIFIERS - RFQ 5 - RELOCATE SPRINKLER HEADS/PIPING - RFQ 6 - PROVIDE S
Nov 22, 2024P00002$127.4KBASE - ZMP ARTCC MECHANICAL AND ELECTRICAL UPGRADES MODIFICATION NO. 2 RFQ 2 REV 1 - REPLACE OLD VALVES - RFQ 4 - REPLACE FAN COIL - REROUTE WATER LINE MODIFICATION NO. 2 VALVE REPLACEMENT
Jul 1, 2024P00001$133.9KMODIFICATION NO. 1 - ZMP ARTCC MECHANICAL AND ELECTRICAL UPGRADES - ADDITIONAL SCOPE TO PERFORM PSB CURTAINWALL REPLACEMENT
Dec 12, 20230$449.3KZMP ARTCC MECHANICAL AND ELECTRICAL UPGRADES - PREFERRED SDVOSB SET ASIDE

Research next steps

  1. Check the stated set-aside against the solicitation and current certifications.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.