Federal contract award

697DCK24F01123

DESIGN BUILD PROJECT TO MODERNIZE THE SLC ATCT, TRACON BUILDING AND BASE BUILDING.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Transportation
Office697DCK REGIONAL ACQUISITIONS SVCS
NAICS236220 — Commercial and Institutional Building Construction
PSCZ1BA — MAINTENANCE OF AIR TRAFFIC CONTROL TOWERS
Parent award / vehicle697DCK23G00009
Set-asideSMALL BUSINESS SET ASIDE - TOTAL
Pricing typeFIRM FIXED PRICE
Obligations$10.8M
Current contract value$10.8M
Potential contract value / ceiling$10.8M
Start dateSep 18, 2024
Current end dateSep 30, 2027
Potential end dateSep 30, 2027
Latest award activitySep 9, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 14 of 14 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Sep 11, 2026P00013$18.2KDESIGN BUILD PROJECT TO MODERNIZE THE SLC ATCT, TRACON BUILDING AND BASE BUILDING.
Sep 9, 2026P00012$124.7KDESIGN BUILD PROJECT TO MODERNIZE THE SLC ATCT, TRACON BUILDING AND BASE BUILDING.
Aug 28, 2026P00011$36.2KDESIGN BUILD PROJECT TO MODERNIZE THE SLC ATCT, TRACON BUILDING AND BASE BUILDING.
Jun 22, 2026P00010$51.5KDESIGN BUILD PROJECT TO MODERNIZE THE SLC ATCT, TRACON BUILDING AND BASE BUILDING.
May 26, 2026P00009$117.8KDESIGN BUILD PROJECT TO MODERNIZE THE SLC ATCT, TRACON BUILDING AND BASE BUILDING.
Apr 23, 2026P00008$87.1KDESIGN BUILD PROJECT TO MODERNIZE THE SLC ATCT, TRACON BUILDING AND BASE BUILDING.
Feb 3, 2026P00007$0DESIGN BUILD PROJECT TO MODERNIZE THE SLC ATCT, TRACON BUILDING AND BASE BUILDING.
Jan 7, 2026P00006$71.6KDESIGN BUILD PROJECT TO MODERNIZE THE SLC ATCT, TRACON BUILDING AND BASE BUILDING.
Dec 17, 2025P00005$0DESIGN BUILD PROJECT TO MODERNIZE THE SLC ATCT, TRACON BUILDING AND BASE BUILDING.
Nov 5, 2025P00004$6.8KDESIGN BUILD PROJECT TO MODERNIZE THE SLC ATCT, TRACON BUILDING AND BASE BUILDING.
Sep 4, 2025P00003$162.3KDESIGN BUILD PROJECT TO MODERNIZE THE SLC ATCT, TRACON BUILDING AND BASE BUILDING.
Aug 1, 2025P00002$49.2KDESIGN BUILD PROJECT TO MODERNIZE THE SLC ATCT, TRACON BUILDING AND BASE BUILDING.
Jul 28, 2025P00001$84.6KDESIGN BUILD PROJECT TO MODERNIZE THE SLC ATCT, TRACON BUILDING AND BASE BUILDING.
Sep 18, 20240$10.0MDESIGN BUILD PROJECT TO MODERNIZE THE SLC ATCT, TRACON BUILDING AND BASE BUILDING.

Estimated positioning window

Oct 25, 2026 – Mar 30, 2027

Recompete signal:
75/100

Why this recompete signal

Contract timing and recorded acquisition signals at the time of calculation.

Stored score: 75/100. Available recorded signals: 70 points.

Contract end 2027-09-30 (340 days from calculation)
+35 points
103 historical awards in this buyer and category group
+15 points
14 recorded award transactions
+10 points
Latest award action: 2026-09-09
+5 points
Parent award identifier recorded
+5 points
Solicitation identifier recorded
+0 points
Linked official forecast
+0 points
Calculated on
2026-10-25 10:18:04.631876+00:00

The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.

Rule-based research score; it does not measure your chance of winning.

This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.

USAspending award record

. Rule-based research score; positioning dates are estimates.

Recompete score calculated Oct 25, 2026.

Research next steps

  1. Check the linked forecast or SAM for a confirmed solicitation and current timing.
  2. Confirm the ordering vehicle and your eligibility or a qualified teaming route.
  3. Check the stated set-aside against the solicitation and current certifications.
  4. Review the award scope and buyer evidence before making a bid/no-bid decision.