Federal contract award

697DCK26C00126

CONTRACT FOR THE GRISWOLD VALVE REMOVAL PROJECT AT BOSTON CENTER NASHUA, NH. PROJECT IS TO SHUT DOWN AND DRAIN THE BOILER PLANT IN ORDER TO REMOVE TWO FLOW-RESTRICTING GRISWOLD VALVES, INSTALL FLOW MONITORING CAPABILITY, REFILL AND RESTART THE BOILE

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Transportation
Office697DCK REGIONAL ACQUISITIONS SVCS
NAICS238220 — Plumbing, Heating, and Air-Conditioning Contractors
PSCY1BC — CONSTRUCTION OF RADAR AND NAVIGATIONAL FACILITIES
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$90.6K
Current contract value$90.6K
Potential contract value / ceiling$90.6K
Start dateApr 29, 2026
Current end dateSep 14, 2026
Potential end dateSep 14, 2026
Latest award activityMay 6, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 1 of 1 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
May 6, 20260$90.6KCONTRACT FOR THE GRISWOLD VALVE REMOVAL PROJECT AT BOSTON CENTER NASHUA, NH. PROJECT IS TO SHUT DOWN AND DRAIN THE BOILER PLANT IN ORDER TO REMOVE TWO FLOW-RESTRICTING GRISWOLD VALVES, INSTALL FLOW MONITORING CAPABILITY, REFILL AND RESTART THE BOILE

Research next steps

  1. Check the stated set-aside against the solicitation and current certifications.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.