Federal contract award
6982AF23C000007
CO FLAP US36(1) DOWNTOWN ESTES PARK LOOP CONSTRUCTION CONTRACT FOR ROADWAY RECONSTRUCTION, REHAB, AND BRIDGE REPLACEMENT
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Transportation |
| Office | 6982AF CENTRAL FEDERAL LANDS DIVISI |
| NAICS | 237310 — Highway, Street, and Bridge Construction |
| PSC | Y1LB — CONSTRUCTION OF HIGHWAYS, ROADS, STREETS, BRIDGES, AND RAILWAYS |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $28.2M |
| Current contract value | $28.2M |
| Potential contract value / ceiling | $28.2M |
| Start date | Dec 5, 2022 |
| Current end date | Mar 12, 2025 |
| Potential end date | Mar 12, 2025 |
| Latest award activity | Feb 11, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 14 of 14 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Feb 11, 2026 | P00013 | $0 | THIS MODIFICATION ADDS A PAY ITEM FOR WORK ASSOCIATED WITH UPGRADING THE ELECTRICAL WIRING FOR THE POST OFFICE PARKING STREETLIGHT TO MEET THE LATEST NATIONAL ELECTRIC CODE (NEC) REQUIREMENTS. THIS MODIFICATION HAS A NET VALUE OF $0.00 AND DOES NOT C |
| Jun 3, 2025 | P00012 | $0 | THIS MODIFICATION COMPENSATES THE CONTRACTOR FOR WORK ASSOCIATED WITH UPGRADES TO THE PEDESTRIAN STREETLIGHT WIRING AT ELKHORN AND RIVERSIDE IN ESTES PARK, COLORADO. THIS MODIFICATION HAS A NET VALUE OF -$0.01 AND DOES NOT CHANGE THE CONTRACT COMPLET |
| Apr 21, 2025 | P00011 | $0 | THIS MODIFICATION IS BEING EXECUTED TO COMPENSATE THE CONTRACTOR FOR ADDITIONAL EFFORTS TO EXCAVATE FOR STREET LIGHT FOUNDATIONS L-01, L-02, L-03, -L04 AND L-10 LOCATED ON THE MORAINE AVENUE SOUTHBOUND BYPASS LANE THROUGH THE NEW ROUNDABOUT. |
| Apr 2, 2025 | P00010 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO MODIFY THE CONTRACT TO REFLECT THE CONTRACTOR'S NAME CHANGE. |
| Dec 6, 2024 | P00009 | $0 | THIS MODIFICATION COMPENSATES THE CONTRACTOR FOR ADDITIONAL EFFORTS TO PERFORM ROCK EXCAVATION FOR STORM DRAINAGE SYSTEMS A2 AND A3, LOCATED ON MORAINE AVENUE SOUTHBOUND BYPASS LANE THROUGH ROUNDABOUT. THE CONTRACTOR USED A HYDRAULIC EXCAVATOR TO REM |
| Dec 4, 2024 | P00008 | $0 | THIS CONTRACT MODIFICATION IS PREPARED TO COMPENSATE THE CONTRACTOR FOR PROVIDING COLD TEMPERATURE PROTECTION FOR THE SUBGRADE, AGGREGATE BASE, AND PORTLAND CEMENT CONCRETE PAVEMENT (PCCP) PLACED IN WINTER OF 2023. |
| Dec 3, 2024 | P00007 | $0 | THIS MODIFICATION IS BEING EXECUTED TO ADD WORK FOR UPGRADE TO POWER SOURCE FOR THE NEW EAST RIVERSIDE DRIVE/ELKHORN AVENUE TRAFFIC SIGNAL. THIS MODIFICATION DOES NOT ADD TIME TO THE CONTRACT. |
| Nov 14, 2024 | P00006 | $0 | THIS MODIFICATION IS BEING EXECUTED TO CHANGE THE PEDESTRIAN HANDRAIL MATERIAL TYPE AND INSTALL A TRAFFIC SIGNAL EMERGENCY VEHICLE PRE-EMPTION SYSTEM. THIS MODIFICATION ADDS 4 DAYS TO THE CONTRACT. AS A RESULT OF ADDING 4 ADDITIONAL DAYS, THE EARLY C |
| Nov 7, 2024 | P00005 | $0 | THIS MODIFICATION ADDS PAINTING OF SIGNPOSTS, LIGHT POLE POWDER COATING, AND A LIGHT POLE FOUNDATION. ALSO ADDS 14 DAYS TO THE CONTRACT COMPLETION DATE AND ADDS 14 DAYS TO THE EARLY COMPLETION DATE INCENTIVE. |
| Oct 22, 2024 | P00004 | $0 | THIS MODIFICATION ADDS QUANTITY TO AN EXISTING ITEM FOR PAYMENT OF EPOXY COATED REINFORCING STEEL FOR RETAINING WALLS RW-03A\B\C\D, RW-04, RW-05, RW-06, RW-07A\B, RW-08, RW-09, RW-10, AND RW-11. THE CONTRACT WAS IN ERROR AND DID NOT QUANTIFY THE REIN |
| May 30, 2024 | P00003 | $0 | THIS CONTRACT MODIFICATION REVISES THE SPECIAL CONTRACT REQUIREMENTS (SCR) SPECIFICATION SUBSECTION 704.08(B)(1) FOR MINIMUM RESISTIVITY REQUIREMENTS FOR SELECT GRANULAR BACKFILL. THIS IS A $0.00 DOLLAR MODIFICATION AND HAS NO EFFECT ON THE CONTRACT |
| Aug 15, 2023 | P00002 | $0 | CO FLAP US36(1) DOWNTOWN ESTES PARK LOOP THE PURPOSE FOR THIS MODIFICATION IS TO DE-OBLIGATE ($610,086.07) FUNDS FROM THE FLAP, V200 TASK AND OBLIGATE ($610,086.07) THEM ON THE V24A TASK. |
| Mar 7, 2023 | P00001 | $0 | CO FLAP US36(1) DOWNTOWN ESTES PARK LOOP THIS CONTRACT MODIFICATION ADDS 27 DAYS (15 FOR DELAYED NTP + 12 DAYS FOR HOLIDAY PERIOD OF NON-WORK) TO THE CURRENT COMPLETION DATE AND EXTENDS IT FROM DECEMBER 15, 2024, TO JANUARY 11, 2025. THIS CONTRA |
| Dec 5, 2022 | 0 | $28.2M | CO FLAP US36(1) DOWNTOWN ESTES PARK LOOP CONSTRUCTION CONTRACT FOR ROADWAY RECONSTRUCTION, REHAB, AND BRIDGE REPLACEMENT |
Buyer contacts from matching notices
Matched on exact award/solicitation identifier and awarding agency. Source dates describe the notice, not current contact verification.
| Contact | Role | Published contact methods | Evidence | Source date |
|---|---|---|---|---|
| Ryan Phillips | Contact | CFLAcquisitions@dot.gov | Source | Oct 14, 2022 |
| Ryan Phillips | Contact | CFLAcquisitions@dot.gov | Source | Oct 11, 2022 |
| Ryan Phillips | Contact | CFLAcquisitions@dot.gov | Source | Oct 7, 2022 |
| Ryan Phillips | Contact | CFLAcquisitions@dot.gov | Source | Oct 6, 2022 |
| Ryan Phillips | Contact | CFLAcquisitions@dot.gov | Source | Oct 5, 2022 |
| Ryan Phillips | Contact | CFLAcquisitions@dot.gov | Source | Oct 3, 2022 |
| Ryan Phillips | Contact | CFLAcquisitions@dot.gov | Source | Sep 29, 2022 |
| Ryan Phillips | Contact | CFLAcquisitions@dot.gov | Source | Sep 29, 2022 |
| Ryan Phillips | Contact | CFLAcquisitions@dot.gov | Source | Sep 15, 2022 |
| Ryan Phillips | Contact | CFLAcquisitions@dot.gov | Source | Sep 8, 2022 |
| Ryan Phillips | Contact | CFLAcquisitions@dot.gov | Source | Sep 2, 2022 |
| Ryan Phillips | Contact | CFLAcquisitions@dot.gov | Source | Aug 15, 2022 |