Federal contract award
6982AF24C000013
UT NP CARE 10(2) & 100(1) SCENIC DRIVE & GOOSENECKS ROAD ROAD CONSTRUCTION AND REHABILITATION CONTRACT
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Transportation |
| Office | 6982AF CENTRAL FEDERAL LANDS DIVISI |
| NAICS | 237310 — Highway, Street, and Bridge Construction |
| PSC | Y1LB — CONSTRUCTION OF HIGHWAYS, ROADS, STREETS, BRIDGES, AND RAILWAYS |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $11.3M |
| Current contract value | $11.3M |
| Potential contract value / ceiling | $11.3M |
| Start date | Mar 25, 2024 |
| Current end date | Aug 30, 2025 |
| Potential end date | Aug 30, 2025 |
| Latest award activity | May 21, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 9 of 9 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 21, 2026 | P00008 | $-1.9M | UT NP CARE 10(2) & 100(1) SCENIC DRIVE AND GOOSENECK ROAD THIS MODIFICATION DEOBLIGATES EXCESS FUNDS AND CLOSES OUT THE CONTRACT. |
| Mar 11, 2026 | P00007 | $0 | THIS MODIFICATION PROVIDES FOR A GLOBAL SETTLEMENT AGREEMENT OF THE PROJECT. THIS SETTLEMENT CLOSES ALL ISSUES ON THIS PROJECT. |
| Aug 11, 2025 | P00006 | $469.9K | THIS MODIFICATION ADDS THE CONSTRUCTION OF TEN (10) STONE HEADWALLS TO SCHEDULE A, ON SCENIC DRIVE. THIS MODIFICATION ADDS 229 DAYS TO THE CONTRACT COMPLETION DATE CHANGING IT TO AUGUST 30, 2025. |
| Oct 28, 2024 | P00005 | $0 | THIS CONTRACT MODIFICATION ADDS 18-INCH, 24-INCH, 30-INCH, AND 36-INCH PIPE CULVERTS TO THE PROJECT WORK. DURING GRADING OPERATIONS MANY EXISTING PIPE CULVERTS THAT WERE NOT SCHEDULED FOR WORK IN THIS CONTRACT HAD COLLAPSED OR SHOWED DETERIORATION AN |
| Sep 23, 2024 | P00004 | $0 | THIS MODIFICATION IS BEING EXECUTED TO CHANGE THE METHOD OF MEASUREMENT AND PAYMENT FOR PAY ITEM NO. 30101-0000 AGGREGATE BASE, WHICH INCLUDES ITEM NOS. A0560, X0360, AND Y 0360.THE METHOD OF MEASUREMENT IS CHANGED FROM TON TO CUBIC YARD. |
| Sep 17, 2024 | P00003 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO ADD A 30" CORRUGATED METAL PIPE CULVERT AND TWO END SECTIONS. THIS MODIFICATION DOES NOT ADD TIME AND HAS A NET VALUE OF -$0.04. |
| Jun 25, 2024 | P00002 | $106.0K | THE PURPOSE FOR THIS MODIFICATION IS TO OBLIGATE ADDITIONAL FUNDS FOR A SCHEDULE A VAULT TOILET. INCREASE CLIN 00102 (CON02) 73A7 FUNDS BY $106,000.00 |
| May 2, 2024 | P00001 | $2.4M | THE PURPOSE FOR THIS MODIFICATION IS TO OBLIGATE ADDITIONAL FUNDS EXERCISE AWARD FOR OPTION X AND OPTION Y. |
| Mar 25, 2024 | 0 | $10.3M | UT NP CARE 10(2) & 100(1) SCENIC DRIVE & GOOSENECKS ROAD ROAD CONSTRUCTION AND REHABILITATION CONTRACT |
Buyer contacts from matching notices
Matched on exact award/solicitation identifier and awarding agency. Source dates describe the notice, not current contact verification.
| Contact | Role | Published contact methods | Evidence | Source date |
|---|---|---|---|---|
| Ryan Phillips | Contact | CFLAcquisitions@dot.gov | Source | Mar 25, 2024 |
| Ryan Phillips | Contact | CFLAcquisitions@dot.gov | Source | Jan 22, 2024 |
| Ryan Phillips | Contact | CFLAcquisitions@dot.gov | Source | Jan 11, 2024 |
| Ryan Phillips | Contact | CFLAcquisitions@dot.gov | Source | Jan 11, 2024 |
| Ryan Phillips | Contact | CFLAcquisitions@dot.gov | Source | Jan 10, 2024 |
| Ryan Phillips | Contact | CFLAcquisitions@dot.gov | Source | Dec 7, 2023 |
| Kelly Palmer | Contact | cflacquisitions@dot.gov 7209633500 | Source | Sep 15, 2023 |
| Ryan Phillips | Contact | cflacquisitions@dot.gov 720-963-3500 | Source | Sep 15, 2023 |